Oyster Creek Nuclear Alert: As Floodwaters Fall, More Questions Arise

Oyster Creek Nuclear Generating Station in pre-flood mode. (photo: NRCgov)

New Jersey’s Oyster Creek Nuclear Generating Station remains under an official Alert, a day-and-a-half after the US Nuclear Regulatory Commission declared the emergency classification due to flooding triggered by Hurricane Sandy. An Alert is the second category on the NRC’s four-point emergency scale. Neil Sheehan, a spokesman for the federal regulator, said that floodwaters around the plant’s water intake structure had receded to 5.7 feet at 2:15 PM EDT Tuesday, down from a high of 7.4 feet reached just after midnight.

Water above 6.5 to 7 feet was expected to compromise Oyster Creek’s capacity to cool its reactor and spent fuel pool, according to the NRC. An “Unusual Event,” the first level of emergency classification, was declared Monday afternoon when floodwaters climbed to 4.7 feet.

Though an emergency pump was brought in when water rose above 6.5 feet late Monday, the NRC and plant owner Exelon have been vague about whether it was needed. As of this writing, it is still not clear if Oyster Creek’s heat transfer system is functioning as designed.

As flooding continued and water intake pumps were threatened, plant operators also floated the idea that water levels in the spent fuel pool could be maintained with fire hoses. Outside observers, such as nuclear consultant Arnie Gundersen, suspected Oyster Creek might have accomplished this by repurposing its fire suppression system (and Reuters later reported the same), though, again, neither Exelon nor regulators have given details.

Whether the original intake system or some sort of contingency is being used, it appears the pumps are being powered by backup diesel generators. Oyster Creek, like the vast majority of southern New Jersey, lost grid power as Sandy moved inland Monday night. In the even of a site blackout, backup generators are required to provide power to cooling systems for the reactor–there is no such mandate, however, for spent fuel pools. Power for pool cooling is expected to come either from the grid or the electricity generated by the plant’s own turbines.

As the NRC likes to remind anyone who will listen, Oyster Creek’s reactor was offline for fueling and maintenance. What regulators don’t add, however, is that the reactor still needs cooling for residual decay heat, and that the fuel pool likely contains more fuel and hotter fuel as a result of this procedure, which means it is even more at risk for overheating. And, perhaps most notably, with the reactor shutdown, it is not producing the electricity that could be used to keep water circulating through the spent fuel pool.

If that sounds confusing, it is probably not by accident. Requests for more and more specific information (most notably by the nuclear watchdog site SimplyInfo) from Exelon and the NRC remain largely unanswered.

Oyster Creek was not the only nuclear power plant dealing with Sandy-related emergencies. As reported here yesterday, Nine Mile Point Unit 1 and Indian Point Unit 3–both in New York–each had to scram because of grid interruptions triggered by Monday’s superstorm. In addition, one of New Jersey’s Salem reactors shut down when four of six condenser circulators (water pumps that aid in heat transfer) failed “due to a combination of high river level and detritus from Hurricane Sandy’s transit.” Salem vented vapor from what are considered non-nuclear systems, though as noted often, that does not mean it is completely free of radioactive components. (Salem’s other reactor was offline for refueling.)

Limerick (PA) reactors 1 and 2, Millstone (CT) 3, and Vermont Yankee all reduced power output in response to Superstorm Sandy. The storm also caused large numbers of emergency warning sirens around both Oyster Creek and the Peach Bottom (PA) nuclear plant to fail.

If you thought all of these problems would cause nuclear industry representatives to lay low for a while, well, you’d be wrong:

“Our facilities’ ability to weather the strongest Atlantic tropical storm on record is due to rigorous precautions taken in advance of the storm,” Marvin Fertel, chief executive officer of the Nuclear Energy Institute, a Washington-based industry group, said yesterday in a statement.

Fertel went on to brag that of the 34 reactors it said were in Sandy’s path, 24 survived the storm without incident.

Or, to look at it another way, during a single day, the heavily populated eastern coast of the Unite States saw multiple nuclear reactors experience problems. And that’s in the estimation of the nuclear industry’s top lobbyist.

Or, should we say, the underestimation? Of the ten reactors not in Fertel’s group of 24, seven were already offline, and the industry is not counting them. So, by Fertel’s math, Oyster Creek does not figure against what he considers success. Power reductions and failed emergency warning systems are also not factored in, it appears.

This storm–and the trouble it caused for America’s nuclear fleet–comes in the context of an 18-month battle to improve nuclear plant safety in the wake of the multiple meltdowns and continuing crisis at Japan’s Fukushima Daiichi nuclear facility. Many of the rules and safety upgrades proposed by a US post-Fukushima taskforce are directly applicable to problems resulting from Superstorm Sandy. Improvements to flood preparation, backup power regimes, spent fuel storage and emergency notification were all part of the taskforce report–all of which were theoretically accepted by the Nuclear Regulatory Commission. But nuclear industry pushback, and stonewalling, politicking and outright defiance by pro-industry commissioners has severely slowed the execution of post-Fukushima lessons learned.

The acolytes of atom-splitting will no doubt point to the unprecedented nature of this massive hybrid storm, echoing the “who could have predicted” language heard from so many after the earthquake and tsunami that started the Fukushima disaster. Indeed, such language has already been used–though, granted, in a non-nuclear context–by Con Edison officials discussing massive power outages still afflicting New York City:

At a Consolidated Edison substation in Manhattan’s East Village, a gigantic wall of water defied elaborate planning and expectations, swamped underground electrical equipment, and left about 250,000 lower Manhattan customers without power.

Last year, the surge from Hurricane Irene reached 9.5 feet at the substation. ConEd figured it had that covered.

The utility also figured the infrastructure could handle a repeat of the highest surge on record for the area — 11 feet during a hurricane in 1821, according to the National Weather Service. After all, the substation was designed to withstand a surge of 12.5 feet.

With all the planning, and all the predictions, planning big was not big enough. Sandy went bigger — a surge of 14 feet.

“Nobody predicted it would be that high,” said ConEd spokesman Allan Drury.

In a decade that has seen most of the warmest years on record and some of the era’s worst storms, there needs to be some limit on such excuses. Nearly a million New York City residents (including this reporter) are expected to be without electricity through the end of the week. Residents in the outer boroughs and millions in New Jersey could be in the dark for far longer. Having a grid that simply survives a category 1 hurricane without a Fukushima-sized nuclear disaster is nothing to crow about.

The astronomical cost of restoring power to millions of consumers is real, as is the potential danger still posed by a number of crippled nuclear power plants. The price of preventing the current storm-related emergencies from getting worse is also not a trivial matter, nor are the radioactive isotopes vented with every emergency reactor scram. All of that should be part of the nuclear industry’s report card; all of that should raise eyebrows and questions the next time nuclear is touted as a clean, safe, affordable energy source for a climate change-challenged world.

UPDATE: The AP is reporting that the NRC has now lifted the emergency alert at Oyster Creek.

Hurricane Sandy Brings Wind, Rain and Irony to US Nuclear Plants

Hurricane Sandy’s projected path as of 9 AM, Monday. (map courtesy of NOAA)

With Hurricane Sandy projected to make landfall hundreds of miles to the south and the predicted storm surge still over 24 hours away, New York City completely shuttered its mass transit system early Sunday evening. By 7 PM, all subway service was halted for only the second time in history. The fear, according to state authorities, is that heavy rainfall or the expected six-to-eleven-foot increase in tide levels would flood subway tunnels, stranding trains at various points across the 842 miles of track.

Fearing similar flooding, the Washington, DC, Metro is also expected to suspend service for all of Monday.

Twelve hours after NYC shut down its subways, at 7 AM Monday, with Hurricane Sandy lashing the Mid-Atlantic coast with heavy rain and 85 mph winds, at least a half-dozen commercial nuclear reactors lie in the storm’s projected path–and the US Nuclear Regulatory Commission has yet to issue any specific orders to the facilities it supposedly oversees. In fact, check out the NRC’s twitter feed or look at its website, and the only reference you will find to what has been dubbed “Frankenstorm” is the recently posted cancellation notice for a public hearing that was supposed to convene on Tuesday, October 30.

The subject of that meeting? The Fort Calhoun Nuclear Generating Station.

The Fort Calhoun plant sits on the Missouri River, on the eastern edge of Nebraska, near the town of Blair. Fort Calhoun’s single pressurized water reactor was shutdown for refueling in April of last year, but floods during the summer of 2011 encircled the facility and caused a series of dangerous incidents. A breach in water berms surrounded transformers and auxiliary containment buildings with two feet of water. Around that same time, a fire shut down power to Fort Calhoun’s spent fuel pools, stopping the circulation of cooling water for 90 minutes and triggering a “red event,” the second most severe classification. Outside of its reactor, the Nebraska facility is home to approximately 800,000 pounds of high-level radioactive waste. To this day, Fort Calhoun is offline and awaiting further evaluation by the NRC.

That a hearing on a flooded plant has been postponed because of the threat of flooding near NRC offices seems like the height of irony, but it pales next to the comparison of safety preparedness measures taken by New York’s Metropolitan Transit Authority for a subway and the federal government’s approach to a fleet of nuclear reactors.

That is not to say that the NRC is doing nothing. . . not exactly. Before the weekend, regulators let it be known that they were considering sending extra inspectors to some nuclear facilities in Sandy’s path. Additionally, regional officials stressed that plant operators were doing walk downs to secure any outside equipment that might become a sort of missile in the event of high winds. It is roughly the equivalent of telling homeowners to tie down their lawn furniture.

And it seems to be understood, at least at the nuclear plants in southern New Jersey, that reactors should be shutdown at least two hours before winds reach 74 mph.

To all that, the NRC made a point of assuring the public that reactor containment buildings could withstand hurricane-force winds, or any odd piece of “lawn furniture” that might be hurled at them.

That’s nice, but hardly the point.

Containment breech is always a concern, but it is not the main issue today. A bigger worry are SBOs–Station Black Outs–loss-of-power incidents that could impede a plant’s capacity to cool its reactors or spent fuel pools, or could interfere with operators’ ability to monitor everything that is going on inside those areas.

As reported last year, Hurricane Irene caused an emergency shutdown at Maryland’s Calvert Cliffs nuclear plant when aluminum siding torn off by high winds shorted out the main transformer and caused an explosion, damaging structures and equipment. Calvert Cliffs was one of the facilities that had chosen not to reduce output or shutdown in advance of Irene–especially alarming because just days before that storm, plant operators had reported trouble with its diesel backup generators.

Irene caused other problems, beyond loss of electricity to millions of consumers, public notification sirens in two emergency preparedness zones were disabled by the storm.

In sum, storm damage triggered a scram at a plant with faulty backup generators. If power had not been restored, backup would have failed, and the rising temperatures in the reactors and fuel pools would have necessitated an evacuation of the area–only evacuation would have been hampered because of widespread power outages and absent sirens.

The worst did not happen last year at Calvert Cliffs, but the damage sustained there was substantial, and the incident should serve as a cautionary tale. Shutting down a nuclear reactor doesn’t prevent every problem that could result from a severe storm, but it narrows the possibilities, reduces some dangers, and prevents the excessive wear and tear an emergency shutdown inflicts on an aging facility.

Calvert Cliffs is again in the line of fire–as are numerous other plants. Hurricane Sandy will likely bring high winds, heavy rain and the threat of flooding to nuclear facilities in Virginia, Maryland, New Jersey, New York and Connecticut. Given last year’s experiences–and given the high likelihood that climate change will bring more such events in years to come–it might have been expected that the NRC would have a more developed policy.

Instead, as with last year’s Atlantic hurricane, federal regulators have left the final decisions to private sector nuclear operators–operators that have a rather poor track record in evaluating threats to public safety when actions might affect their bottom line.

At the time of this writing, the rain in New York City is little more than a drizzle, winds are gusting far below hurricane strength, and high tide is still over ten hours away. Hurricane Sandy is over 300 miles to the south.

But Gotham is a relative ghost town. The subway turnstiles are locked; city busses are nowhere to be seen.

At the region’s nuclear facilities, however–at North Anna, Hope Creek, Salem and Oyster Creek, at Calvert Cliffs, Indian Point and Millstone–there is no such singular sense of better-safe-than-sorry mission.

In New York, it can be argued that the likes of Governor Andrew Cuomo and Mayor Michael Bloomberg have gone overboard, that they have made decisions based not just on safety, but on fears of political fallout and employee overtime. But in the Nuclear Regulatory Commission’s northeast region, there is no chance of that kind of criticism–one might even say there is no one to criticize, because it would appear that there is no one in charge.