Oyster Creek Nuclear Alert: As Floodwaters Fall, More Questions Arise

Oyster Creek Nuclear Generating Station in pre-flood mode. (photo: NRCgov)

New Jersey’s Oyster Creek Nuclear Generating Station remains under an official Alert, a day-and-a-half after the US Nuclear Regulatory Commission declared the emergency classification due to flooding triggered by Hurricane Sandy. An Alert is the second category on the NRC’s four-point emergency scale. Neil Sheehan, a spokesman for the federal regulator, said that floodwaters around the plant’s water intake structure had receded to 5.7 feet at 2:15 PM EDT Tuesday, down from a high of 7.4 feet reached just after midnight.

Water above 6.5 to 7 feet was expected to compromise Oyster Creek’s capacity to cool its reactor and spent fuel pool, according to the NRC. An “Unusual Event,” the first level of emergency classification, was declared Monday afternoon when floodwaters climbed to 4.7 feet.

Though an emergency pump was brought in when water rose above 6.5 feet late Monday, the NRC and plant owner Exelon have been vague about whether it was needed. As of this writing, it is still not clear if Oyster Creek’s heat transfer system is functioning as designed.

As flooding continued and water intake pumps were threatened, plant operators also floated the idea that water levels in the spent fuel pool could be maintained with fire hoses. Outside observers, such as nuclear consultant Arnie Gundersen, suspected Oyster Creek might have accomplished this by repurposing its fire suppression system (and Reuters later reported the same), though, again, neither Exelon nor regulators have given details.

Whether the original intake system or some sort of contingency is being used, it appears the pumps are being powered by backup diesel generators. Oyster Creek, like the vast majority of southern New Jersey, lost grid power as Sandy moved inland Monday night. In the even of a site blackout, backup generators are required to provide power to cooling systems for the reactor–there is no such mandate, however, for spent fuel pools. Power for pool cooling is expected to come either from the grid or the electricity generated by the plant’s own turbines.

As the NRC likes to remind anyone who will listen, Oyster Creek’s reactor was offline for fueling and maintenance. What regulators don’t add, however, is that the reactor still needs cooling for residual decay heat, and that the fuel pool likely contains more fuel and hotter fuel as a result of this procedure, which means it is even more at risk for overheating. And, perhaps most notably, with the reactor shutdown, it is not producing the electricity that could be used to keep water circulating through the spent fuel pool.

If that sounds confusing, it is probably not by accident. Requests for more and more specific information (most notably by the nuclear watchdog site SimplyInfo) from Exelon and the NRC remain largely unanswered.

Oyster Creek was not the only nuclear power plant dealing with Sandy-related emergencies. As reported here yesterday, Nine Mile Point Unit 1 and Indian Point Unit 3–both in New York–each had to scram because of grid interruptions triggered by Monday’s superstorm. In addition, one of New Jersey’s Salem reactors shut down when four of six condenser circulators (water pumps that aid in heat transfer) failed “due to a combination of high river level and detritus from Hurricane Sandy’s transit.” Salem vented vapor from what are considered non-nuclear systems, though as noted often, that does not mean it is completely free of radioactive components. (Salem’s other reactor was offline for refueling.)

Limerick (PA) reactors 1 and 2, Millstone (CT) 3, and Vermont Yankee all reduced power output in response to Superstorm Sandy. The storm also caused large numbers of emergency warning sirens around both Oyster Creek and the Peach Bottom (PA) nuclear plant to fail.

If you thought all of these problems would cause nuclear industry representatives to lay low for a while, well, you’d be wrong:

“Our facilities’ ability to weather the strongest Atlantic tropical storm on record is due to rigorous precautions taken in advance of the storm,” Marvin Fertel, chief executive officer of the Nuclear Energy Institute, a Washington-based industry group, said yesterday in a statement.

Fertel went on to brag that of the 34 reactors it said were in Sandy’s path, 24 survived the storm without incident.

Or, to look at it another way, during a single day, the heavily populated eastern coast of the Unite States saw multiple nuclear reactors experience problems. And that’s in the estimation of the nuclear industry’s top lobbyist.

Or, should we say, the underestimation? Of the ten reactors not in Fertel’s group of 24, seven were already offline, and the industry is not counting them. So, by Fertel’s math, Oyster Creek does not figure against what he considers success. Power reductions and failed emergency warning systems are also not factored in, it appears.

This storm–and the trouble it caused for America’s nuclear fleet–comes in the context of an 18-month battle to improve nuclear plant safety in the wake of the multiple meltdowns and continuing crisis at Japan’s Fukushima Daiichi nuclear facility. Many of the rules and safety upgrades proposed by a US post-Fukushima taskforce are directly applicable to problems resulting from Superstorm Sandy. Improvements to flood preparation, backup power regimes, spent fuel storage and emergency notification were all part of the taskforce report–all of which were theoretically accepted by the Nuclear Regulatory Commission. But nuclear industry pushback, and stonewalling, politicking and outright defiance by pro-industry commissioners has severely slowed the execution of post-Fukushima lessons learned.

The acolytes of atom-splitting will no doubt point to the unprecedented nature of this massive hybrid storm, echoing the “who could have predicted” language heard from so many after the earthquake and tsunami that started the Fukushima disaster. Indeed, such language has already been used–though, granted, in a non-nuclear context–by Con Edison officials discussing massive power outages still afflicting New York City:

At a Consolidated Edison substation in Manhattan’s East Village, a gigantic wall of water defied elaborate planning and expectations, swamped underground electrical equipment, and left about 250,000 lower Manhattan customers without power.

Last year, the surge from Hurricane Irene reached 9.5 feet at the substation. ConEd figured it had that covered.

The utility also figured the infrastructure could handle a repeat of the highest surge on record for the area — 11 feet during a hurricane in 1821, according to the National Weather Service. After all, the substation was designed to withstand a surge of 12.5 feet.

With all the planning, and all the predictions, planning big was not big enough. Sandy went bigger — a surge of 14 feet.

“Nobody predicted it would be that high,” said ConEd spokesman Allan Drury.

In a decade that has seen most of the warmest years on record and some of the era’s worst storms, there needs to be some limit on such excuses. Nearly a million New York City residents (including this reporter) are expected to be without electricity through the end of the week. Residents in the outer boroughs and millions in New Jersey could be in the dark for far longer. Having a grid that simply survives a category 1 hurricane without a Fukushima-sized nuclear disaster is nothing to crow about.

The astronomical cost of restoring power to millions of consumers is real, as is the potential danger still posed by a number of crippled nuclear power plants. The price of preventing the current storm-related emergencies from getting worse is also not a trivial matter, nor are the radioactive isotopes vented with every emergency reactor scram. All of that should be part of the nuclear industry’s report card; all of that should raise eyebrows and questions the next time nuclear is touted as a clean, safe, affordable energy source for a climate change-challenged world.

UPDATE: The AP is reporting that the NRC has now lifted the emergency alert at Oyster Creek.

Book Salon – Joseph Mangano, Author of Mad Science: The Nuclear Power Experiment

[Note: On Saturday afternoon, I hosted FDL Book Salon, featuring a live Q&A with Joseph Mangano, author of Mad Science: The Nuclear Power Experiment. This is a repost of that discussion.]

In December of 1962, Consolidated Edison, New York City’s main purveyor of electricity, announced that it had submitted an official proposal to the US Atomic Energy Commission (the AEC, the precursor to today’s Nuclear Regulatory Commission) for the construction of a nuclear power plant on a site called Ravenswood. . . in Queens. . . on the East River. . . directly across from the United Nations. . . within five miles of roughly five million people.

Ravenswood became the site of America’s first demonstrations against nuclear power. It inspired petitions to President John F. Kennedy and NYC Mayor Robert Wagner, and the possibility of a nuclear reactor in such a densely populated area even invited public skepticism from the pro-nuclear head of the AEC, David Lilienthal. Finally, after a year of pressure, led by the borough’s community leaders, Con Edison withdrew their application.

But within three years, reports suggested Con Ed had plans to build a nuclear plant under Central Park. After that idea was roundly criticized, the utility publicly proposed a reactor complex under Welfare Island (now known as Roosevelt Island), instead.

Despite the strong support of Laurence Rockefeller, the brother of New York State’s governor, the Welfare Island project disappeared from Con Ed’s plans by 1970. . . soon to be replaced by the idea of a nuclear “jetport”–artificial islands to be built in the ocean just south of New York City that would host a pair of commercial reactors.

Does that sound like madness? Well, from today’s perspective–with Three Mile Island, Chernobyl, and now Fukushima universally understood as synonyms for disaster–it probably does. But there was a time before those meltdowns when nuclear power still had a bit of a glow, when, despite (or because of) the devastation from the atomic bombs dropped on Japan, many believed that the atom’s awesome power could be harnessed for good; a time when dangerous and deadly mishaps at a number of the nation’s earlier reactors were easily excused or kept completely secret.

In Mad Science: The Nuclear Power Experiment, Joseph Mangano returns to that time, and then methodically pulls back the curtain on the real history of nuclear folly and failure, and the energy source that continues to masquerade as clean, safe, and “too cheap to meter.”

From Chalk River, in Canada, the world’s first reactor meltdown, through Idaho’s EBR-1, Waltz Mill, PA, Santa Susana’s failed Sodium Reactor Experiment, the Idaho National Lab explosion that killed three, Fermi-1, which almost irradiated Detroit, and, of course, Three Mile Island, Mad Science provides a chilling catalog of nuclear accidents, all of which were disasters in their own right, and all of which illustrate a troubling pattern of safety breeches followed by secrecy and lies.

Nuclear power’s precarious existence is not, of course, just a story for the history books, and Mangano also details the state of America’s 104 remaining reactors. So many of today’s plants have problems, too, but perhaps the maddest thing about the mad science of civilian atomic power is that science often plays a minor role in decisions about the technology’s future.

From its earliest days, this supposedly super-cheap energy was financially unsustainable. By the mid-1950s, private insurers had turned their back on nuclear facilities, fearing the massive payouts that would follow any accident. The nuclear industry turned to the US government, and in 1957, the Price-Anderson Act limited a plant’s liability to an artificially low but apparently insurable figure–any damage beyond that would be covered by US taxpayers. Shippingport, America’s first large-scale commercial nuclear reactor, was built entirely with government money, and that is hardly an isolated story. Even before the Three Mile Island meltdown, Wall Street had walked away from nuclear energy, meaning that no new reactors could be built without massive federal loan guarantees.

Indeed, the cost of construction, when piled on top of the cost of fueling, skilled labor, operation and upkeep, made the prospect of opening a new nuclear plant financially unpalatable. So, as Mangano explains, nuclear utilities turned to another strategy for making their vertical profitable, one familiar to any student of late Western capitalism. Rather than build, energy companies would instead buy. Since the 1990s, the nuclear sector has seen massive consolidation. Mergers and acquisitions have created nuclear mega-corporations, like Exelon, Duke, and Entergy, which run multiple reactors across many facilities in many states. And the supposed regulators of the industry, the NRC, has encouraged this behavior by rubberstamping dozens upon dozens of 20-year license extensions, turning reactors that were supposed to be nearing the end of their functional lives into valuable assets.

But the pain of nuclear power isn’t only measured in meltdowns and money. Whether firing on all cylinders (as it were) or falling apart, nuclear plants have proven to be dangerous to the populations they are supposed to serve. Joseph Mangano, an epidemiologist by trade, and director of the Radiation and Public Health Project (RPHP), has made a career out of trying to understand the immediate and long-term effects of nuclear madness, be it from fallout, leaks, or the “permissible levels” of radioactive isotopes that are regularly released from reactors as part of normal operation.

As I mentioned earlier this week, Mangano and the RPHP are the inheritors of the Baby Tooth Survey, the groundbreaking examination of strontium levels in children born before, during and after the age of atmospheric nuclear bomb tests. The discovery of high levels of Sr-90, a radioactive byproduct of uranium fission, in the baby teeth of children born in the 1950s and ’60s led directly to the Partial Test Ban Treaty in 1963.

Mangano’s work has built on the original survey, linking elevated Sr-90 levels to cancer, and examining the increases in strontium in the bodies of children that lived close to nuclear power plants. And all of this is explained in great detail in Mad Science.

The author has also applied his expertise to the fallout from the ongoing Fukushima disaster. Last December, Mangano and Janette Sherman published a peer-reviewed article in the International Journal of Health Sciences (PDF) stating that in the 14 weeks following the start of the Japanese nuclear crisis, an estimated 14,000 excess deaths in the United States could be linked to radioactive fallout from Fukushima Daiichi. (RPHP has since revised that estimate–upward–to almost 22,000 deaths (PDF).)

That last study is not specifically detailed in Mad Science, but I hope we can touch on it today–along with some of the many equally maddening “experiments” in nuclear energy production that Mangano carefully unwraps in his book.

[Click here to read my two-hour chat with Joe Mangano.]

End-of-Summer News Puts Nuclear Renaissance on Permanent Vacation

Calvert Cliffs Nuclear Power Plant, Units 1 & 2, near Lusby Maryland. (photo: NRCgov)

The Nuclear Regulatory Commission cannot issue a license for the construction and operation of a new nuclear reactor in Maryland–that is the ruling of the NRC’s Atomic Safety and Licensing Board (ASLB) handed down Thursday.

In their decision, the ASLB agreed with intervenors that the Calvert Cliffs 3 reactor project planned for the shores of Chesapeake Bay violated the Atomic Energy Act’s prohibition against “foreign ownership, control, or domination.” UniStar, the parent company for the proposal, is wholly owned by French energy giant Électricité de France (EDF).

EDF had originally partnered with Constellation Energy, the operator of two existing Calvert Cliffs reactors, but Constellation pulled out of the project in 2010. At the time, Constellation balked at government requirements that Constellation put $880 million down on a federal loan guarantee of $7.6 billion (about 12 percent). Constellation wanted to risk no more than one or two percent of their own capital, terms the feds were then willing to meet if Constellation and EDF could guarantee the plant’s completion. Constellation also found that requirement too onerous.

Constellation has since been purchased by Exelon.

The ASLB decision technically gives EDF 60 days to find a new American partner, but given the history and the current state of the energy market, new suitors seem highly unlikely. It marks only the second time a license has been denied by the ASLB. (The first, for the Byron, Illinois plant in 1984 was overturned on appeal. Byron opened the next year, and Illinois’s groundwater has never been the same.) The NRC also declined to grant a license to the South Texas Project late last year when US-based NRG Energy (corporate ID courtesy of the Department of Redundancy Department) pulled out of the project, leaving Japanese-owned Toshiba as the only stakeholder.

The Calvert Cliffs intervenors were led by the Nuclear Information and Resource Service (NIRS), which has been fighting Calvert Cliffs 3 almost since its inception. NIRS was joined by Beyond Nuclear, Public Citizen and Southern Maryland CARES.

Michael Mariotte, Executive director of NIRS, called Thursday’s decision “a blow to the so-called ‘nuclear renaissance,'” noting that back in 2007, when permit requests were submitted for Calvert Cliffs 3, the project was considered the “flagship” of a coming fleet of new reactors. “Now,” said Mariotte, “it is a symbol for the deservedly failed revival of nuclear power in the US.”

A symbol, yes, but far from the only symbol.

Earlier in the week, Exelon notified the Nuclear Regulatory Commission that it would withdraw its application for an “early site permit” for a proposed nuclear facility near Victoria, Texas. A combined construction and operating license was originally sought for two reactors back in 2008, but by 2010, with demand down and nuclear costs continuing to skyrocket, Exelon backed off that request, essentially downgrading it to “just keeping a toe in the water” status.

Now, with the price of a new nuke plant climbing higher still–even though the economy remains sluggish–and with natural gas prices continuing to fall, that toe has been toweled dry. “Today’s withdrawal brings an end to all project activity,” said an Exelon statement issued Tuesday.

And on Monday, the operators of the troubled San Onofre Nuclear Generating Station let it be known that they would start removing the radioactive fuel from Unit 3 sometime in September. Unit 3 has been offline since it scrammed after a heat exchange tube leaked radioactive steam at the end of January. Later inspection revealed that numerous tubes on the unit, as well as on its previously shut-down twin, showed alarming and dangerous amounts of wear.

Removing the fuel rods all-but-confirms what most experts already knew: SONGS 3 will never come back online. Southern California Edison, the plant’s majority operator, might not want to admit that, but earlier in August, SCE announced plans for 730 layoffs, roughly a third of the plant’s workforce. That size of reduction makes repairing, testing and restarting both San Onofre reactors unfeasible. Or, to look at it through the other end of the telescope, as David Lochbaum, director of the Union of Concerned Scientists put it, “reducing the scope of required work at the jobsite is a good thing to do before discharging workers.”

Mothballing Unit 3 will reduce the workload, but with the entire facility offline for most of this year, SONGS is already an economic sinkhole. Strangely, despite failing to generate a single kilowatt of energy in eight months, SCE and co-owner San Diego Gas & Electric have continued to collect $54 million of revenue every month from California ratepayers.

The California Public Utilities Commission has to investigate rate cuts when a plant fails to deliver for nine months (so, officially, November and December, for the two SONGS reactors), but that process would start sooner if it were determined that a reactor would never come back into service. Neither San Onofre reactor will restart before the end of the year, and it is now clearer than a San Diego summer sky that the number 3 reactor never will. Scientists know this, engineers know this, utilities commissioners know this, and even Southern California Edison knows this–but SCE won’t say it because that would hasten the start of rate rollbacks.

Calvert Cliffs being in the news this time of year also calls to mind how well nuclear plants do in hurricanes. . . as in, not very well at all. Last year, as Hurricane Irene marched up the Atlantic coast, the two existing reactors at Calvert Cliffs had to scram when a dislodged piece of siding caused a short in the main transformer and an “unanticipated explosion within the Protected Area resulting in visible damage to permanent structures or equipment.”

As fate would have it, this year’s “I” storm, Isaac, necessitated the shutdown of Entergy’s Waterford plant, outside of New Orleans. In fact, many plants are required to shutdown when facing winds in excess of 74 mph, “rendering them,” as Beyond Nuclear put it, “a liability, rather than an asset during a natural disaster.”

And Hurricane Isaac was but one possible symptom of a warming climate that has proven problematic for nuclear plants this summer. Braidwood, Illinois and Millstone in Connecticut had to curtail output or temporarily shutdown this summer because the source water used for cooling the reactors rose above prescribed limits. With summer temperatures expected to climb even more in coming years–and with droughts also anticipated–incidents like these (and like those at Hope Creek, New Jersey, and Limerick, Pennsylvania, in 2010) will become more frequent, leaving nuclear power less able to deliver electricity during the months when it is most in demand.

Of course, the summer of 2012 has also had its share of what might be called “classic” nuclear plant problems–power supply failures, radioactive leaks, and other so-called “unusual incidents.” One of the most recent, yet another accident at Palisades in Michigan:

On Sunday [August 12], Palisades shut down due to a leak of radioactive and acidic primary coolant, escaping from safety-critical control rod drive mechanisms attached to its degraded lid, atop its “worst embrittled reactor pressure vessel in the U.S.”

And all of the above has happened during a summer when the NRC finally acknowledged (or, more accurately, when a federal court ordered the NRC to acknowledge) that it could no longer pretend the US had a solution for its nuclear waste storage crisis. The commission has stopped issuing new operating licenses, license extensions and construction licenses until it can craft a plan for dealing with the mountains of spent nuclear fuel continuing to accumulate at nuclear facilities across the country.

So, there is no nuclear renaissance. There wasn’t one before this summer–there wasn’t even one before everyone came to know about the Fukushima disaster. The dangers and costs that have followed nuclear power since its inception have firmly branded it as a technology of the past. The events of 2011 and 2012 have provided more evidence that nuclear power is done as a meaningful energy proposition. The sooner America can also be done with the myth of a possible, sometime, “who knows when,” “maybe next year” nuclear renaissance, the sooner the federal government can stop propping up the unsafe and unviable nuclear industry. And the sooner the US can begin a real technological and economic rebirth.

For Nuclear Power This Summer, It’s Too Darn Hot


You know that expression, “Hotter than July?” Well, this July, July was hotter than July. Depending on what part of the country you live in, it was upwards of three degrees hotter this July than the 20th Century average. Chicago, Denver, Detroit, Indianapolis and St. Louis are each “on a pace to shatter their all-time monthly heat records.” And “when the thermometer goes way up and the weather is sizzling hot,” as the Cole Porter song goes, demand for electricity goes way up, too.

During this peak period, wouldn’t it be great to know that you can depend on the expensive infrastructure your government and, frankly, you as ratepayers and taxpayers have been backstopping all these years? Yeah, that would be great. . . so would an energy source that was truly clean, safe, and too cheap to meter. Alas, to the surprise of no one (at least no one who watches this space), nuclear power, the origin of that catchy if not quite Porter-esque tripartite promise, cannot.

Take, for example, Braidwood, the nuclear facility that supplies much of Chicago with electricity:

It was so hot last week, a twin-unit nuclear plant in northeastern Illinois had to get special permission to continue operating after the temperature of the water in its cooling pond rose to 102 degrees.

It was the second such request from the plant, Braidwood, which opened 26 years ago. When it was new, the plant had permission to run as long as the temperature of its cooling water pond, a 2,500-acre lake in a former strip mine, remained below 98 degrees; in 2000 it got permission to raise the limit to 100 degrees.

The problem, said Craig Nesbit, a spokesman for Exelon, which owns the plant, is not only the hot days, but the hot nights. In normal weather, the water in the lake heats up during the day but cools down at night; lately, nighttime temperatures have been in the 90s, so the water does not cool.

But simply getting permission to suck in hotter water does not make the problem go away. When any thermoelectric plant (that includes nuclear, coal and some gas) has to use water warmer than design parameters, the cooling is less effective, and that loss of cooling potential means that plants need to dial down their output to keep from overheating and damaging core components. Exelon said it needed special dispensation to keep Braidwood running because of the increased demand for electricity during heat waves such as the one seen this July, but missing from the statement is that the very design of Braidwood means that it will run less efficiently and supply less power during hot weather.

Also missing from Exelon’s rationale is that they failed to meet one of the basic criteria for their exception:

At the Union of Concerned Scientists, a group that is generally critical of nuclear power safety, David Lochbaum, a nuclear engineer, said the commission was supposed to grant exemptions from its rules if there was no increase or only a minor increase in risk, and if the situation could not have been foreseen.

The safety argument “is likely solid and justified,’’ he wrote in an e-mail, but “it is tough to argue (rationally) that warming water conditions are unforeseen.’’ That is a predictable consequence of global warming, he said.

Quite. Lochbaum cites two instances from the hot summer of 2010–New Jersey’s Hope Creek nuclear station and Limerick in Pennsylvania each had to reduce output due to intake water that was too warm. In fact, cooling water problems at US thermoelectric generators were widespread along the Mississippi River during the hot, dry summer of 1988.

And the problem is clearly growing. Two months ago, a study published in Nature Climate Change predicted continued warming and spreading drought conditions will significantly reduce thermoelectric output in coming decades:

Higher water temperatures and reduced river flows in Europe and the United States in recent years have resulted in reduced production, or temporary shutdown, of several thermoelectric power plants, resulting in increased electricity prices and raising concerns about future energy security in a changing climate.

. . . .

[The Nature Climate Change study] projects further disruption to supply, with a likely decrease in thermoelectric power generating capacity of between 6-19% in Europe and 4-16% in the United States for the period 2031-2060, due to lack of cooling-water. The likelihood of extreme (>90%) reductions in thermoelectric power generation will, on average, increase by a factor of three.

Compared to other water use sectors (e.g. industry, agriculture, domestic use), the thermoelectric power sector is one of the largest water users in the US (at 40%) and in Europe (43% of total surface water withdrawals). While much of this water is ‘recycled’ the power plants rely on consistent volumes of water, at a particular temperature, to prevent overheating of power plants. Reduced water availability and higher water temperatures – caused by increasing ambient air temperatures associated with climate change – are therefore significant issues for electricity supply.

That study is of course considering all thermoelectric sources, not just nuclear, but the decrease in efficiency applies across the board. And, when it comes to nuclear power, as global temperatures continue to rise and water levels in rivers and lakes continue to drop, an even more disconcerting threat emerges.

When a coal plant is forced to shut down because of a lack of cool intake water, it can, in short order, basically get turned off. With no coal burning, the cooling needs of the facility quickly downgrade to zero.

A nuclear reactor, however, is never really “off.”

When a boiling water reactor or pressurized water reactor (BWR and PWR respectively, the two types that make up the total of the US commercial reactor fleet) is “shutdown” (be it in an orderly fashion or an abrupt “scram”), control rods are inserted amongst the fuel rods inside the reactor. The control rods absorb free neutrons, decreasing the number of heavy atoms getting hit and split in the fuel rods. It is that split, that fission, that provides the energy that heats the water in the reactor and produces the steam that drives the electricity-generating turbines. Generally, the more collisions, the more heat generated. An increase in heat means more steam to spin a turbine; fewer reactions means less heat, less steam and less electrical output. But it doesn’t mean no heat.

The water that drives the turbines also cools the fuel rods. It needs to circulate and somehow get cooled down when it is away from the reactor core. Even with control rods inserted, there are still reactions generating heat, and that heat needs to be extracted from the reactor or all kinds of trouble ensues–from too-high pressure breaching containment to melting the cladding on fuel rods, fires, and hydrogen explosions. This is why the term LOCA–a loss of coolant accident–is a scary one to nuclear watchdogs (and, theoretically, to nuclear regulators, too).

So, even when they are not producing electricity, nuclear reactors still need cooling. They still need a power source to make that cooling happen, and they still need a coolant, which, all across the United States and most of the rest of the world, means water.

Water that is increasingly growing too warm or too scarce. . . at least in the summer. . . you know, when it’s hot. . . and demand for electricity increases.

In fact, Braidwood is not the only US plant that has encountered problems this sultry season:

[A] spokeswoman for the Midwest Independent System Operator, which operates the regional grid, said that another plant had shut down because its water intake pipes were now above the water level of the body from which it draws its cooling water. Another is “partially curtailed.”

That spokeswoman can’t, it seems, tell us which plants she is talking about because that information “is considered competitive.” (Good to know that the Midwest Independent System Operator has its priorities straight. . . . Hey, that sounds like a hint! Anyone in the Midwest notice a nearby power plant curtailing operations?)

So, not isolated. . . and also not a surprise–not to the Nature Climate Change people this year, and not to the industry, itself. . . 17 years ago. The Electric Power Research Institute (EPRI), a non-profit group of scientists and engineers funded by the good folks who generate electricity (a group that has a noticeable overlap with the folks that own nuclear plants), released a study in 1995 that specifically warned of the threat a warming climate posed to electrical generation. The EPRI study predicted that rising levels of atmospheric carbon dioxide would make power production less efficient and more expensive, while at the same time increasing demand.

And climate predictions have only grown more dire since then.

Add to that mix one more complicating factor: when the intake water is warmer, the water expelled by the plant is warmer, too. And there are environmental protections in many areas that limit how hot that “waste” water can be. There have been instances in the past where thermoelectric plants have had to curtail production because their exhaust water exceeded allowable temperatures.

And yet, despite a myriad of potential problems and two decades of climate warnings, it is sobering to note that none of the US reactors were built to account for any of this. . . because all American nuclear reactors predate these revelations. That is not to say nuclear operators haven’t had 20 years (give or take) to plan for these exigencies, but it is to say that, by-and-large, they haven’t. (Beyond, that is, as described above, simply lobbying for higher water temperature limits. That’s a behavior all too recognizable when it comes to nuclear operators and regulators–when nuclear plants can’t meet requirements, don’t upgrade the procedures or equipment, just “upgrade” the requirements.)

But, rather than using all this knowledge to motivate a transition away from nuclear power, rather than using the time to begin decommissioning these dinosaurs, nuclear operators have instead pushed for license extensions–an additional 20 years beyond the original 40-year design. And, to date, the Nuclear Regulatory Commission has yet to reject a single extension request.

And now the nuclear industry–with the full faith and credit of the federal government–is looking to double down on this self-imposed ignorance. The “Advanced Passive” AP1000 reactors approved earlier this year for Georgia’s Plant Vogtle (and on track for South Carolina, too) may be called “advanced,” but they are still PWRs and they still require a large reserve of cool, circulating water to keep them operating and nominally safe.

The government is offering $8.3 billion of financing for the Georgia reactors at rock-bottom rates, and with very little cash up front from the plant owners. There have already been numerous concerns about the safety of the AP1000 design and the economic viability of the venture; factor in the impact of climate change, and the new Vogtle reactors are pretty much the definition of “boondoggle”–a wasteful, pointless project that gives the appearance of value while in reality delivering none. It is practically designed to fail, leaving the government (read: taxpayers and ratepayers) holding the bag.

But as a too-darn-hot July ends, that’s the woo being pitched by the nuclear industry and its government sweethearts. Rather than invest the money in technologies that actually thrive during the long, hot days of summer, rather than invest in improved efficiency and conservation programs that would both create jobs and decrease electrical demand (and carbon emissions), rather than seizing the moment, making, as it were, hay while the sun shines, it seems the US will choose to bury its head in the sand and call it shade.

Nuclear power was already understood to be dirty, dangerous and absurdly expensive, even without the pressures of climate change. Far from being the answer to growing greenhouse gas emissions, the lifecycle of nuclear power–from mining and milling to transport and disposal–has turned out to be a significant contributor to the problem. And now, the global weirding brought on by that problem has made nuclear even more precarious–more perilous and more pricy–and so an even more pernicious bet.

According to the Kinsey Report, every average man you know would prefer to play his favorite sport when the temperature is low. But when the thermometer goes way up and the weather is sizzling hot, a gob for his squab, a marine for his beauty queen, a GI for his cutie-pie–and now it turns out–the hour for nuclear power is not.

‘Cause it’s too darn hot.
It’s too. Darn. Hot.

Does the Netroots Care about Nuclear Power?

Van Jones speaking to the faithful at this year’s Netroots Nation conference in Providence, RI – June 9, 2012.

On Thursday, June 7, as hundreds of online journalists and activists gathered in Providence, Rhode Island for the seventh annual Netroots Nation conference to discuss what were deemed the most pressing issues of the day, a smaller group made up of nuclear industry representatives and officials from the Nuclear Regulatory Commission and the US Department of Energy got together 400 miles south to discuss matters they thought even more urgent. While the attendees in the Ocean State were getting training on “how to navigate the action-packed schedule at Netroots Nation [and] survive on two hours sleep (and still be alert for a day of panels!),” owners of the nation’s aging nuclear facilities pursued doubling the length of new operating licenses, floating the possibility that reactors will be allowed to run into their 80th year–twice the original design life of most plants.

As bloggers, organizers, pundits and politicians were discovering the charms of the Beehive of Industry (yes, that is one of Providence’s nicknames), inspectors at Davis-Besse, the oft-discussed, always troubled nuclear power plant near Toledo, Ohio were reporting what they termed a “pinhole” leak releasing about a gallon of radioactive coolant every 10 minutes. The reactor had been shut down for refueling, maintenance and safety inspections, but was supposed to restart last week. . . before the leak was discovered in a pipe weld. (Though the reason behind the leak has yet to be determined, FirstEnergy, Davis-Besse’s owner, has now resumed the restart. . . without so much as a raised eyebrow from regulators.)

This incident at Davis-Besse comes not so very long after the Ohio primary, where the safety of the plant and trustworthiness of its owners and regulators was an issue in the race between two sitting Democratic members of Congress–Representatives Dennis Kucinich and Marcy Kaptur. Forced to run against each other because of redistricting, the plight of Davis-Besse became a defining issue between the two, with Kucinich calling for the plant to remain off-line until the cause of cracks in the containment structure was determined, while Kaptur affirmed her faith in FirstEnergy. Kaptur argued that the failing facility meant jobs for the struggling district–a district that was drawn to favor Kaptur’s old base–and in the end, beat Kucinich for the Democratic nod.

Following this latest breach in safety, Representative-for-another-six-months Kucinich has petitioned the Nuclear Regulatory Commission’s Inspector General (PDF) for an investigation into the NRC’s lax supervision of Davis-Besse.

As the netroots community and representatives of organized labor pondered in Providence whither the union movement in the wake of the Wisconsin recall results, 250 actual union workers, locked out of their jobs at Massachusetts Pilgrim nuclear plant (a short drive from the Rhode Island Convention Center), some for as long as 10 weeks, were filing a five-point grievance with the National Labor Relations Board. The union accused Pilgrim’s operator, Entergy, of coercive and threatening behavior leading up to a June 2 vote on a new labor contract. The workers overwhelmingly rejected the contract a week after the NRC granted Entergy a 20-year license extension for the plant–and 10 days after Pilgrim had to scram because of reduced vacuum in the plant’s condenser.

That there would be problems at a plant where replacement workers have been complaining that they are being asked to do jobs outside their expertise hardly seems surprising. That an ongoing labor action, safety concerns and licensing fight happening just two counties away from Providence would not be an issue at the Netroots Nation convention is a bit more vexing.

While conventioneers in Providence listened to New York Attorney General Eric Schneiderman explain his relative lack of action on the foreclosure fraud crisis as somehow part of what he called a “transformational moment,” members of Pilgrim Watch, a citizen’s group opposed to the Massachusetts nuclear plant, were in court demanding that regulators do more to require post-Fukushima lessons learned be incorporated in required upgrades to Pilgrim’s GE Mark I boiling water reactor (the exact same design as those at Fukushima Daiichi). Activist groups have mounted similar (and additional) legal challenges to the relicensing of Vermont Yankee, another ancient Mark I reactor well into its break-down phase. And in New York, public activism mounts as the Indian Point reactors approach their relicensing hearing.

In fact, Friday, as Netroots Nation attendees wondered why there was a 90-minute gap in the midday schedule (word is conference organizers were hoping to bag the president or vice president as a lunchtime keynote, and the extra time was allotted for additional security. In case you missed it, the closest the conference got to any high-level White House official was a new campaign video, introduced on tape by Obama), the DC Court of Appeals handed down an important decision that could have broad implications for the future of domestic commercial nuclear power. A three-judge panel unanimously ruled that the Nuclear Regulatory Commission was negligent in the way it evaluated plant safety because regulators assumed a solution to the country’s long-term radioactive waste storage crisis when none currently exists.

If you were watching your twitter feed, you might have caught this. If you were sitting in on any of Friday afternoon’s Netroots panels, this ruling probably didn’t come up.

Indeed, throughout the three-plus days of panels, training sessions, caucuses and keynotes, attendees quite likely heard no mention of nuclear power, its persistent threats to safety, its drastic drain on the budget, its onerous oppression of workers or its brazen gouging of rate-payers. For, while there were well over 100 panels, and dozens of other training sessions and caucuses, nothing on the schedule even made a passing attempt to address nuclear energy here in the United States or the ongoing (and growing) crisis of radioactive contamination from Fukushima spreading across the globe.

It would be one thing if this were purely fodder for wonks and science geeks, but as demonstrated above, and in over a year’s worth of columns, nuclear power touches on many (if not most) of the issues considered to be core concerns of the netroots movement. Corporate greed, captured government, worker rights, environmental justice, and a lazy legacy media–its all part and parcel of the nuclear narrative.

And it might not be worth a few precious hours of conference schedule if the fight against nuclear power and its acolytes were a lost cause, but in this post-Fukushima moment (and, yes, we are still in it), the country and the world stand at a crossroads. While the US government seems hell-bent on backstopping a failing, flailing industry, other countries are using this crisis to step back from the next potential nuclear nightmare and commit to a cleaner, renewable energy future. Meanwhile, here in the United States, engaged communities of activists and concerned citizens are organizing to fight on the local level for the protections their federal government has failed to deliver.

The appeals court decision on Friday is a monument, really, to the years of hard work put in by individuals and organizations across the country–and it is a monumental opportunity to learn from this success and build the future of the anti-nuclear movement.

It is a movement that could benefit greatly from the online organizing tools that have breathed so much life into the netroots, but the netroots, too, could learn a few things from the anti-nuclear movement. Providence, with its physical proximity to Pilgrim, and its temporal proximity to so many developments on the nuclear front, would have seemed like a golden opportunity. But the organizers of Netroots Nation appeared to have other priorities.

While the good folks at NIRS–the Nuclear Information and Resource Service–where awarded a booth in the exhibition hall at the Providence convention center, veterans of the conference know there is quite a different level of engagement when it comes to the booths, versus what happens at panels and speeches. (This is to take nothing away from NIRS, which had a table filled with great information, much of which can also be found on their website.)

Fired up?

Some noise was made, quite publicly, as a matter of fact, about this year’s Netroots convention being friendlier to the Obama administration. “I think people are generally on board [with Obama’s reelection effort],” said Raven Brooks, the executive director of Netroots, as he explained to Talking Points Memo that this year’s convention would be relatively free of the confrontation that met White House Communications Director Dan Pfeiffer at the 2011 conference.

“People are fired up about 2012,” said Mary Rickles, who is communications director for Netroots, noting in the same TPM article that she expected an administration presence at this year’s conference. (Again, unless you count Schneiderman, there was none.)

Inside the convention center, Van Jones–briefly part of the Obama administration until driven out by a rightwing witch-hunt, and cofounder of Rebuild the Dream–headlined the last night of speeches. Jones, himself a longtime advocate for renewable energy, instead turned to a theme he has hit often in recent years: that while some might be disappointed with the pace of progress, in the end, it is not Obama’s failing, it is ours. But this time, it being an election year, and everyone thusly “fired up,” Jones put it this way: “We have two tasks: to re-elect the president and re-energize the movement to hold the president accountable.”

Quoting Jones in an email announcing next year’s convention, Brooks underscored the point:

After November has come and gone, our job of pushing for the strongest possible progressive policies will begin in earnest. In short, we’ve got to step up our game.

Inspiring thoughts, perhaps, but ones completely contrary to the way electoral politics has worked in this country about as far back as anyone can remember. Making demands of office-seekers after you’ve pledged your vote is not just cart-before-the-horse, it’s asinine and ass-backwards.

The netroots played a roll in the election of Barack Obama in 2008, though in the eyes of the now-POTUS, not an overly large one. After the election, Team Obama moved quickly to rein in the less-predictable elements of its grassroots campaign while one-by-one riding roughshod over most of the issues that mattered to left-leaning bloggers and online activists. Previous NetNat attendees had a right to boo Obama surrogates, and the folks charged with re-electing the president should be taught to fear that wrath–if not through activism, at least by way of apathy.

Mitt Romney would no doubt make a dismal president–but that is not the point. This election will be decided by turnout, and the Obama campaign will need to motivate parts of his base such as the netroots with reasons to get out and vote for his second term. If online activists want something from Obama in return for going to the polls, the time to demand that, the time to get that on paper–or in pixels–is before election day, not after.

After, Obama doesn’t need you anymore. It’s called a lame duck term for many reasons, but one of them is that the president can easily duck any kind of obligation some might feel he should have to his blandly loyal netizens.

Which brings us back to nuclear power and Netroots Nation. It is not a secret that one of Obama’s great benefactors in past elections has been Exelon, the nuclear giant that not only gave heavily to the 2008 campaign, but once employed both former Obama Chief of Staff Rahm Emanuel and David Axelrod, once a senior Obama advisor and now Communications Director for his 2012 campaign. Obama’s steadfast support for nuclear power–making the point, not once, but twice, in the first weeks after the Fukushima crisis began, to publicly assure that the US commitment to nuclear was strong–now puts him at odds with many countries in the industrialized world, but, more important here, it has always put him at odds with many in the online progressive community. It would be sad to think that conference organizers decided against any anti-nuclear content in an effort to keep this year’s Netroots Nation “onboard” with and “fired up” about a possible administration presence.

But it would be even sadder to think that the fault lies not in these self-anointed stars, but in ourselves. While chances are if you are reading this you have at least some degree of interest in nuclear issues, is it possible that what once was called the “blogosphere” (but now should be considered something more) does not see nuclear power, the looming environmental catastrophe and financial sinkhole it presents, as relevant? Is it that the almighty and always invisible atom is just not as juicy as, say, fracking, or anything with the word “occupy” in it?

That would be a shame–and a mistake–for it is all part of a piece. The work of occupiers across this country over the last year is to be applauded, but some of the things central to the protests, a broken system, a captured government filthy with corporate cash, are central to the fight against nuclear power, as well. And while hydrofracking represents a tremendous threat to our water supply and our climate, and so should be protested full bore, its current profitability might make it less sensitive to activism than nuclear power at this point in its history.

Without government support–without the federal loan guarantees, the Price-Anderson indemnity, state and local tax breaks and rate subsidies–the commercial nuclear power industry would collapse. There would be few demands for license renewals because few plants would turn a profit.

And without a government-run long-term waste repository, the nuclear industry faces even more safety and financial concerns. The lack of storage options is actually a crisis for nuclear operators–and a threat to the safety of a majority of Americans. What this country does with its atomic waste has always been a political issue, too–and it has played out on the political stage throughout this past year. It is an issue that is very sensitive to old-time, easy to grasp, electoral politics, and so it is one sensitive to the newfangled tools of internet organizing.

So, between environmentalists and budget wonks, between regulatory hawks and electoral junkies, and between old-line environmental activists and 21st Century online organizers there is much to discuss. Let’s hope that no matter who is running for whatever office next year, the netroots, and the Netroots Nation conference, find the time and space–and the political will–to engage the dirty, dangerous and expensive threat of nuclear power.

*  *  *

[Full disclosure: I had submitted a panel proposal for the 2012 Netroots Nation conference, and though it was given consideration and, I am told, was in the running till the end, it was not included in the final schedule. The panel was to be called “Clean, Safe, and Too Cheap to Meter? Countering Nuclear’s Lies in a Post-Fukushima Landscape,” and while I was disappointed at not having this opportunity, the far bigger concern for me was that conference organizers chose not to include any sessions on nuclear issues at all. One year’s personal slight is not really a big deal; ignoring the obvious and broad importance of this topic, however, signals a bigger problem.]

Too Cheap to Meter, Too Expensive to Compete

“Clean, safe, and too cheap to meter.” This sunny tagline from the early days of atomic energy has more recently become the quickest way to sum up how dark and dismal its prospects are today–as in, nuclear power has proven itself to be unclean, unsafe, and prohibitively expensive. “Clean, safe and too cheap to meter” now sounds less like boastful marketing, and more like a schoolyard taunt.

The numbers of ways nuclear power plants have betrayed their Madison Avenue mantra has pretty much been the backbeat of this column for nearly ten months now, and 2012 keeps up the cadence.

Exelon Corporation, the nation’s largest owner of nuclear facilities, has already hit a sour note. . . or two.

First, Exelon and Constellation Energy, another major nuclear operator that Exelon agreed to buy last April, have just seen Citigroup downgrade their stock from “buy” to “neutral.” The reason this time, it seems, is not due to the shaky future of nuclear holdings, but instead due to the falling price of natural gas. Gas prices have hit a two-year low thanks to the glut of gas from a nation gone frack-happy.

But why should a Citigroup not worry about the value of nuclear stocks when current problems have required costly shutdowns and repairs, and future improvements that might (might) be required post-Fukushima will necessitate more capital outflow? One need look no further than the same Exelon portfolio, as reflected in a separate story out just one week later:

The U.S. Nuclear Regulatory Commission wants Exelon Corporation to detail its plan regarding a decommissioning fund shortfall for the Limerick Unit 1 nuclear power plant in Pottstown.

“Once we receive the (request for additional information) response, we will make a determination regarding reasonable assurance of adequate decommissioning funding for the plant,” said Neil Sheehan, NRC Public Affairs, via email on Wednesday.

Sheehan said Exelon planned to request rate relief from the Pennsylvania Public Utilities Commission later this year to address the deficit.

“The relief, if approved, would take effect at the beginning of 2013,” Sheehan said.

In other words, a nuclear facility isn’t only ridiculously expensive while it is up and running, generating some power–and so, in theory, some revenue–a nuclear plant is a massive liability for years (decades, really) after it is shut down.

Decommissioning a plant is a process that the Nuclear Regulatory Commission requires operators to finish within 60 years. Yes, it can take that long to safely dismantle a facility, store its moderately radioactive parts and entomb its massively radioactive reactor shell. The cost, as estimated by the NRC itself, is “$300 million or more.”

Indeed, the emphasis should be on “more.” The NRC’s lowball figure not only assumes everything goes smoothly and there are no nasty discoveries, like, say, radioactive contamination of surrounding ground or water, it assumes a constant dollar value over the life (death?) of the decommission. Take note, for instance, that the fund for the decommissioning of one Limerick reactor is at present required to be over $628 million.

But again, why would that not more seriously affect the rating of a company like Exelon, with its vast stable of aged, faulty reactors? Because Exelon, as is the case for all its nuclear brethren, doesn’t expect to have shoulder the costs by themselves–if at all.

Feeling a little light in the decommissioning fund? Do not fear! As pointed out in the story above, Exelon expects rate relief. In other words, Pennsylvania power consumers will pick up the tab in the form of increased electric bills.

Worried the rate hike won’t quite cover it? No problem! As the NRC hints at here and has proven elsewhere, when push comes to dangerous, radioactive shove, the federal government will cover any shortfalls. After all, the alternative–a halfway or half-assed shutdown–is not an acceptable policy option.

Concerned that even with a rate hike and a government bailout something still might go wrong, resulting in pricey lawsuits? Hush, now! Thanks to the Price-Anderson Act, the liability of the nuclear plant operator is remarkably limited.

This is all part-and-parcel of the standard obfuscation procedure and pass-the-buck accounting that allows the nuclear industry to pretend to compete in the energy marketplace. Exelon executives no doubt love to praise the free market, but they are possibly the only ones that get away for anything close to free. Their taxes are discounted, their infrastructure is subsidized, their loans are guaranteed, and their accidents are indemnified, all by state and federal governments, which means all by taxpayers–taxpayers already paying up front for higher energy bills.

Lest this story be misinterpreted, the answer is not, of course, to permit more fracking to continue to drive down the price of natural gas–that option is as rife with dangers as it is ridiculously shortsighted. No, the answer is to take into account all of the money that really goes into nuclear power generation when costing out energy options. Take just a fraction of what the US government expends to backstop atomic energy and invest it instead in improved efficiency, conservation programs, and truly renewable alternatives, and then see what power source can really claim the mantle of clean, safe, and too cheap to meter.

The Party Line – September 23, 2011: In Post-Fukushima Reality, What is the Future, and Who is Winning It?

Beginning a story with a correction for what might seem a technical detail might not provide the most attention-grabbing lede, but it opens the door to a broader, and important, observation.

Last week’s column contained reference to “large nuclear power-generating nations,” and then listed Australia as part of that group. That, as pointed out by reader Dgdonovan, was incorrect:

Australia is not a large nuclear power producing nation, in fact none of Australia’s electricity is produced by nuclear power. Australia is a large uranium producing nation, however.

Indeed, while Australia may posses nearly a quarter of the world’s remaining uranium deposits, it has not commissioned a single industrial-scale nuclear reactor for electrical power generation. While the ongoing crisis at Japan’s Fukushima Daiichi plant makes that look prudent, given the expansion of nuclear power over the last 50 years, it does seem odd.

Australia is hardly an industrial backwater. A member of the G20, Australia is the world’s 13th largest economy in terms of GDP. And it is not as if Australia has not considered building nuclear plants, most recently about five years ago. But nuclear power has never gotten off the ground in Australia for a rather basic reason: it is not supported by a majority of its people.

What the public wants, however, (as some recent events in the US seem to indicate) is not always what the public gets. Also required is a mechanism for the electorate to impose their will.

As previously observed, in the aftermath of the Japanese disaster, German Prime Minister Angela Merkel committed her country to phasing out nuclear power generation in relatively short order, choosing to instead invest in renewables and efficiency. Merkel may have come to this decision based on the facts as now understood post Fukushima, but German domestic politics almost certainly came under consideration, too.

Merkel’s ruling coalition in the Bundestag currently includes her own party, the Christian Democrats (CDU), and the rightwing Free Democratic Party (FDP). By every indication, the FDP is heading for substantial losses in the next federal election, so the CDU will need a new coalition partner to keep Merkel in power. The most productive option is expected to be the Greens, and to woo them, Merkel found an opportune moment to move on a core Green Party issue.

Australia’s system is not identical to Germany’s, but the parliamentary (or Westminster) plan of the lower house introduces some of the same power dynamics. (Liberal-National Coalition PM John Howard proposed developing nuclear power in 2006; his party lost to anti-nuke Labor in 2007.) Federal and most regional elections are also decided by “preferential voting” (also known as IRV, or “instant runoff”). This form of democracy tends to give voters more options, and allows tertiary parties, and their issues, to gain a foothold in the system. Australia also accords a great deal of autonomy to its six state governments, where, for instance, it would be virtually impossible for the federal Australian government to put a nuclear power plant in a state if that state’s government had rejected it.

Contrast this with the United States, where, rather than responding to the new, post-Fukushima realities, the Nuclear Regulatory Commission has signaled it is “full speed ahead” on the relicensing of old nuclear facilities (many of which are nearly identical to the Fukushima reactors; all of which are reaching the ends of their projected lifespans). Seabrook, in Connecticut New Hampshire, has just been granted permission to proceed toward relicensing, and it looks like re-upping the Massachusetts Pilgrim plant will also be moving ahead. This movement runs counter to the NRC’s own recent task force report advocating a new safety regime that incorporates lessons learned from Japan. And this relicensing also runs counter to substantial objections from state governments, nuclear watchdogs, and community activists.

Shouldn’t the chief regulatory agency wait until its new, proposed regulations are in place before giving out licenses for another 20 years of potentially dangerous operation? Under a governmental system that draws its regulators from the industry it regulates and funds its two-party, first-past-the-post elections with money from that industry, it appears not.

And regulatory protocol is not the only point of contrast. In Germany, the marketplace has already recognized the changing reality. Siemens, a German industrial giant, has announced that it is getting out of the nuclear power business:

It [Siemens] will build no further nuclear plants and is canceling its nuclear joint venture with Russia’s Rosatom. Siemens built all 17 of Germany’s existing nuclear plants. Siemens chief executive, Peter Loescher, (pictured) praised the Merkel government’s decision to close all its nuclear plants by 2022 and aim for an 80% to 100% renewable energy economy by 2050, calling it “a project of the century.”

Siemens recognizes that without government support, and without an automatic customer, there is no profit in nuclear power.

In the United States, where President Obama (a beneficiary of large campaign contributions from nuclear power companies) went out of his way to affirm the US commitment to nuclear generation immediately following the Japanese quake and tsunami, and where the federal government continues to offer loan guarantees for maintaining and operating nuclear plants, a very different picture is emerging:

Exelon Corporation and Constellation Energy have filed for Federal Energy Regulatory Commission (FERC) approval of their proposed merger. In the filing, the companies commit themselves to divesting three of Constellation’s non-nuclear power plants totaling [sic] 2648 MWe in a step to ensure the merger will not cause power market or competitive concerns in the PJM (Pennsylvania, Jersey, Maryland) Power Pool in which they operate.

Constellation is the owner of the Calvert Cliffs nuclear facility in Maryland, which has recently come under scrutiny (OK, closer scrutiny, it has a long history of safety concerns) because of an emergency shutdown triggered by a transformer explosion during Hurricane Irene. Exelon, itself the product of a merger brokered by former White House Chief of Staff and current Chicago Mayor Rahm Emanuel, was one of Barack Obama’s largest campaign contributors. Exelon already operates more US nuclear plants than any other power company.

And this isn’t the only consolidation move in the US power sector. Duke Energy and Progress Energy, companies that operate nuclear facilities throughout the southeast, are seeking to form the country’s largest electric utility.

The Exelon-Constellation deal is facing opposition from Maryland’s Governor, Martin O’Malley, while the Duke-Progress merger has raised questions in North Carolina. But the final say on whether either deal goes through rests with FERC, the Federal Energy Regulatory Commission.

FERC is comprised of five commissioners, each appointed by the president to a five-year term (in theory, anyway–one commissioner is still there, despite his term supposedly ending in June). As currently constituted, three members are George W. Bush appointees, two were picked by President Obama (though that does not necessarily predict how they will act). FERC’s decisions are final, and are not subject to any kind of Congressional vote.

The differences are stark. In Germany, where electoral realities have forced to the government to take an honest look at nuclear safety, market realities have delineated a path away from nuclear power and toward a renewable energy economy. In the US, where government is not only insulated from popular opinion but also beholden to corporate largess, elected officials, regulators and industry work hand-in-hand to perpetuate dangerous, expensive and inefficient technologies (while, on Capitol Hill, House Republicans vote to slash already threadbare programs meant to encourage renewable energy development).

In an age where so many economies are desperately trying not to lose any more ground in the present, could it be that the ones more responsive to their rank-and-file electorates are the ones in the best position to (to borrow a quickly forgotten phrase) win the future?