Oyster Creek Nuclear Alert: As Floodwaters Fall, More Questions Arise

Oyster Creek Nuclear Generating Station in pre-flood mode. (photo: NRCgov)

New Jersey’s Oyster Creek Nuclear Generating Station remains under an official Alert, a day-and-a-half after the US Nuclear Regulatory Commission declared the emergency classification due to flooding triggered by Hurricane Sandy. An Alert is the second category on the NRC’s four-point emergency scale. Neil Sheehan, a spokesman for the federal regulator, said that floodwaters around the plant’s water intake structure had receded to 5.7 feet at 2:15 PM EDT Tuesday, down from a high of 7.4 feet reached just after midnight.

Water above 6.5 to 7 feet was expected to compromise Oyster Creek’s capacity to cool its reactor and spent fuel pool, according to the NRC. An “Unusual Event,” the first level of emergency classification, was declared Monday afternoon when floodwaters climbed to 4.7 feet.

Though an emergency pump was brought in when water rose above 6.5 feet late Monday, the NRC and plant owner Exelon have been vague about whether it was needed. As of this writing, it is still not clear if Oyster Creek’s heat transfer system is functioning as designed.

As flooding continued and water intake pumps were threatened, plant operators also floated the idea that water levels in the spent fuel pool could be maintained with fire hoses. Outside observers, such as nuclear consultant Arnie Gundersen, suspected Oyster Creek might have accomplished this by repurposing its fire suppression system (and Reuters later reported the same), though, again, neither Exelon nor regulators have given details.

Whether the original intake system or some sort of contingency is being used, it appears the pumps are being powered by backup diesel generators. Oyster Creek, like the vast majority of southern New Jersey, lost grid power as Sandy moved inland Monday night. In the even of a site blackout, backup generators are required to provide power to cooling systems for the reactor–there is no such mandate, however, for spent fuel pools. Power for pool cooling is expected to come either from the grid or the electricity generated by the plant’s own turbines.

As the NRC likes to remind anyone who will listen, Oyster Creek’s reactor was offline for fueling and maintenance. What regulators don’t add, however, is that the reactor still needs cooling for residual decay heat, and that the fuel pool likely contains more fuel and hotter fuel as a result of this procedure, which means it is even more at risk for overheating. And, perhaps most notably, with the reactor shutdown, it is not producing the electricity that could be used to keep water circulating through the spent fuel pool.

If that sounds confusing, it is probably not by accident. Requests for more and more specific information (most notably by the nuclear watchdog site SimplyInfo) from Exelon and the NRC remain largely unanswered.

Oyster Creek was not the only nuclear power plant dealing with Sandy-related emergencies. As reported here yesterday, Nine Mile Point Unit 1 and Indian Point Unit 3–both in New York–each had to scram because of grid interruptions triggered by Monday’s superstorm. In addition, one of New Jersey’s Salem reactors shut down when four of six condenser circulators (water pumps that aid in heat transfer) failed “due to a combination of high river level and detritus from Hurricane Sandy’s transit.” Salem vented vapor from what are considered non-nuclear systems, though as noted often, that does not mean it is completely free of radioactive components. (Salem’s other reactor was offline for refueling.)

Limerick (PA) reactors 1 and 2, Millstone (CT) 3, and Vermont Yankee all reduced power output in response to Superstorm Sandy. The storm also caused large numbers of emergency warning sirens around both Oyster Creek and the Peach Bottom (PA) nuclear plant to fail.

If you thought all of these problems would cause nuclear industry representatives to lay low for a while, well, you’d be wrong:

“Our facilities’ ability to weather the strongest Atlantic tropical storm on record is due to rigorous precautions taken in advance of the storm,” Marvin Fertel, chief executive officer of the Nuclear Energy Institute, a Washington-based industry group, said yesterday in a statement.

Fertel went on to brag that of the 34 reactors it said were in Sandy’s path, 24 survived the storm without incident.

Or, to look at it another way, during a single day, the heavily populated eastern coast of the Unite States saw multiple nuclear reactors experience problems. And that’s in the estimation of the nuclear industry’s top lobbyist.

Or, should we say, the underestimation? Of the ten reactors not in Fertel’s group of 24, seven were already offline, and the industry is not counting them. So, by Fertel’s math, Oyster Creek does not figure against what he considers success. Power reductions and failed emergency warning systems are also not factored in, it appears.

This storm–and the trouble it caused for America’s nuclear fleet–comes in the context of an 18-month battle to improve nuclear plant safety in the wake of the multiple meltdowns and continuing crisis at Japan’s Fukushima Daiichi nuclear facility. Many of the rules and safety upgrades proposed by a US post-Fukushima taskforce are directly applicable to problems resulting from Superstorm Sandy. Improvements to flood preparation, backup power regimes, spent fuel storage and emergency notification were all part of the taskforce report–all of which were theoretically accepted by the Nuclear Regulatory Commission. But nuclear industry pushback, and stonewalling, politicking and outright defiance by pro-industry commissioners has severely slowed the execution of post-Fukushima lessons learned.

The acolytes of atom-splitting will no doubt point to the unprecedented nature of this massive hybrid storm, echoing the “who could have predicted” language heard from so many after the earthquake and tsunami that started the Fukushima disaster. Indeed, such language has already been used–though, granted, in a non-nuclear context–by Con Edison officials discussing massive power outages still afflicting New York City:

At a Consolidated Edison substation in Manhattan’s East Village, a gigantic wall of water defied elaborate planning and expectations, swamped underground electrical equipment, and left about 250,000 lower Manhattan customers without power.

Last year, the surge from Hurricane Irene reached 9.5 feet at the substation. ConEd figured it had that covered.

The utility also figured the infrastructure could handle a repeat of the highest surge on record for the area — 11 feet during a hurricane in 1821, according to the National Weather Service. After all, the substation was designed to withstand a surge of 12.5 feet.

With all the planning, and all the predictions, planning big was not big enough. Sandy went bigger — a surge of 14 feet.

“Nobody predicted it would be that high,” said ConEd spokesman Allan Drury.

In a decade that has seen most of the warmest years on record and some of the era’s worst storms, there needs to be some limit on such excuses. Nearly a million New York City residents (including this reporter) are expected to be without electricity through the end of the week. Residents in the outer boroughs and millions in New Jersey could be in the dark for far longer. Having a grid that simply survives a category 1 hurricane without a Fukushima-sized nuclear disaster is nothing to crow about.

The astronomical cost of restoring power to millions of consumers is real, as is the potential danger still posed by a number of crippled nuclear power plants. The price of preventing the current storm-related emergencies from getting worse is also not a trivial matter, nor are the radioactive isotopes vented with every emergency reactor scram. All of that should be part of the nuclear industry’s report card; all of that should raise eyebrows and questions the next time nuclear is touted as a clean, safe, affordable energy source for a climate change-challenged world.

UPDATE: The AP is reporting that the NRC has now lifted the emergency alert at Oyster Creek.

Superstorm Sandy Shows Nuclear Plants Who’s Boss

Oyster Creek Nuclear Power Station as seen in drier times. (photo via wikipedia)

Once there was an ocean liner; its builders said it was unsinkable. Nature had other ideas.

On Monday evening, as Hurricane Sandy was becoming Post-Tropical Cyclone Sandy, pushing record amounts of water on to Atlantic shores from the Carolinas to Connecticut, the Nuclear Regulatory Commission issued a statement. Oyster Creek, the nation’s oldest operating nuclear reactor, was under an Alert. . . and under a good deal of water.

An Alert is the second rung on the NRC’s four-point emergency classification scale. It indicates “events are in process or have occurred which involve an actual or potential substantial degradation in the level of safety of the plant.” (By way of reference, the fourth level–a General Emergency–indicates substantial core damage and a potential loss of containment.)

As reported earlier, Oyster Creek’s coolant intake structure was surrounded by floodwaters that arrived with Sandy. Oyster Creek’s 47-year-old design requires massive amounts of external water that must be actively pumped through the plant to keep it cool. Even when the reactor is offline, as was the case on Monday, water must circulate through the spent fuel pools to keep them from overheating, risking fire and airborne radioactive contamination.

With the reactor shut down, the facility is dependant on external power to keep water circulating. But even if the grid holds up, rising waters could trigger a troubling scenario:

The water level was more than six feet above normal. At seven feet, the plant would lose the ability to cool its spent fuel pool in the normal fashion, according to Neil Sheehan, a spokesman for the Nuclear Regulatory Commission.

The plant would probably have to switch to using fire hoses to pump in extra water to make up for evaporation, Mr. Sheehan said, because it could no longer pull water out of Barnegat Bay and circulate it through a heat exchanger, to cool the water in the pool.

If hoses desperately pouring water on endangered spent fuel pools remind you of Fukushima, it should. Oyster Creek is the same model of GE boiling water reactor that failed so catastrophically in Japan.

The NRC press release (PDF) made a point–echoed in most traditional media reports–of noting that Oyster Creek’s reactor was shut down, as if to indicate that this made the situation less urgent. While not having to scram a hot reactor is usually a plus, this fact does little to lessen the potential problem here. As nuclear engineer Arnie Gundersen told Democracy Now! before the Alert was declared:

[Oyster Creek is] in a refueling outage. That means that all the nuclear fuel is not in the nuclear reactor, but it’s over in the spent fuel pool. And in that condition, there’s no backup power for the spent fuel pools. So, if Oyster Creek were to lose its offsite power—and, frankly, that’s really likely—there would be no way cool that nuclear fuel that’s in the fuel pool until they get the power reestablished. Nuclear fuel pools don’t have to be cooled by diesels per the old Nuclear Regulatory Commission regulations.

A site blackout (SBO) or a loss of coolant issue at Oyster Creek puts all of the nuclear fuel and high-level radioactive waste at risk. The plant being offline does not change that, though it does, in this case, increase the risk of an SBO.

But in the statement from the NRC, there was also another point they wanted to underscore (or one could even say “brag on”): “As of 9 p.m. EDT Monday, no plants had to shut down as a result of the storm.”

If only regulators had held on to that release just one more minute. . . .

SCRIBA, NY – On October 29 at 9 p.m., Nine Mile Point Unit 1 experienced an automatic reactor shutdown.

The shutdown was caused by an electrical grid disturbance that caused the unit’s output breakers to open. When the unit’s electrical output breakers open, there is nowhere to “push” or transmit the power and the unit is appropriately designed to shut down under these conditions.

“Our preliminary investigation identified a lighting pole in the Scriba switchyard that had fallen onto an electrical component. This is believed to have caused the grid disturbance. We continue to evaluate conditions in the switchyard,” said Jill Lyon, company spokesperson.

Nine Mile Point Nuclear Station consists of two GE boiling water reactors, one of which would be the oldest operating in the US were it not for Oyster Creek. They are located just outside Oswego, NY, on the shores of Lake Ontario. Just one week ago, Unit 1–the older reactor–declared an “unusual event” as the result of a fire in an electrical panel. Then, on Monday, the reactor scrammed because of a grid disturbance, likely caused by a lighting pole knocked over by Sandy’s high winds.

An hour and forty-five minutes later, and 250 miles southeast, another of the nation’s ancient reactors also scrammed because of an interruption in offsite power. Indian Point, the very old and very contentious nuclear facility less than an hour’s drive north of New York City, shut down because of “external grid issues.” And Superstorm Sandy has given Metropolitan New York’s grid a lot of issues.

While neither of these shutdowns is considered catastrophic, they are not as trivial as the plant operators and federal regulators would have you believe. First, emergency shutdowns–scrams–are not stress-free events, even for the most robust of reactors. As discussed here before, it is akin to slamming the breaks on a speeding locomotive. These scrams cause wear and tear aging reactors can ill afford.

Second, scrams produce pressure that usually leads to the venting of some radioactive vapor. Operators and the NRC will tell you that these releases are well within “permissible” levels–what they can’t tell you is that “permissible” is the same as “safe.”

If these plants were offline, or running at reduced power, the scrams would not have been as hard on the reactors or the environment. Hitting the breaks at 25 mph is easier on a car than slamming them while going 65. But the NRC does not have a policy of ordering shutdowns or reductions in capacity in advance of a massive storm. In fact, the NRC has no blanket protocol for these situations, period. By Monday morning, regulators agreed to dispatch extra inspectors to nuclear plants in harm’s way (and they gave them sat phones, too!), but they left it to private nuclear utility operators to decide what would be done in advance to prepare for the predicted natural disaster.

Operators and the Nuclear Regulatory Commission spokes-folks like to remind all who will listen (or, at least, all who will transcribe) that nuclear reactors are the proverbial house of bricks–a hurricane might huff and puff, but the reinforced concrete that makes up a typical containment building will not blow in. But that’s not the issue, and the NRC, at least, should know it.

Loss of power (SBOs) and loss of coolant accidents (LOCAs) are what nuclear watchdogs were warning about in advance of Sandy, and they are exactly the problems that presented themselves in New York and New Jersey when the storm hit.

The engineers of the Titanic claimed that they had built the unsinkable ship, but human error, corners cut on construction, and a big chunk of ice cast such hubris asunder. Nuclear engineers, regulators and operators love to talk of four-inch thick walls and “defense-in-depth” backup systems, but the planet is literally littered with the fallout of their folly. Nuclear power systems are too complex and too dangerous for the best of times and the best laid plans. How are they supposed to survive the worst of times and no plans at all?

San Onofre: One Leaks, the Other Doesn’t… Yet

For those who thought that, with the new year, nuclear power had turned a page and put its “annus horribilis” behind it–as if the calendar were somehow the friend America’s aging reactors–let’s take a quick look at January 2012.

First, a glance across the Pacific, where the month began with the revelation that the Japanese government purposely downplayed their assessments of the Fukushima disaster–hiding the worst projected scenarios from the public from soon after the March earthquake by classifying the documents as personal correspondence–and ended with discovery of yet another large leak of radioactive water from one of the crippled reactors.

Closer to home, the lone reactor at Wolf Creek, Kansas, was shutdown on January 13 after the failure of a main generator breaker was followed by a still-unexplained loss of power to an electrical transformer. Diesel generators kicked in to run the safety systems until external power was restored, but the plant remains offline while a Nuclear Regulatory Commission inspection team tries to figure out what went wrong.

On the morning of January 30, a power failure caused a reactor at Exelon’s Byron Generating Station to scram, which in turn required a wee bit of venting:

[At] Exelon Nuclear’s Byron Unit 2 atomic reactor near Rockford, IL, primary electrical grid power was lost and safety and cooling systems had to run from emergency backup diesel generators when smoke was seen coming from a switchyard transformer. However, when the plant’s fire brigade responded, they could not find the fire. . . .

As revealed by Exelon’s “Event Report,” offsite firefighters were called in, Unit 1 is still at full power, and Unit 2’s cool down “steam [is] leaving via atmospheric relief valves.”

An initial AP report on the incident stated: “The steam contains low levels of tritium, a radioactive form of hydrogen, but federal and plant officials insisted the levels were safe for workers and the public…[NRC] officials also said the release of tritium was expected. . . .

Because, you know, a scram without some steam is like a coffee with out some cream. Or, as noted in the past, these emergency shutdowns are not subtle, quiet events. They are like slamming the breaks on a speeding car, and they cause all kinds of stresses and strains on reactor systems. Even when backup power kicks in, the process can require the venting of steam to relieve pressure in various parts of the reactor (where depends on the type of reactor and the kind of “unusual event”)–and that steam will often contain tritium, which has molecules so small they can pass from the closed loop that runs through the reactor into the secondary loop (in the case of pressurized water reactors) that powers the turbines.

So, lots of places in the system with varying levels of tritium, which, as Beyond Nuclear points out, is in no way “safe”:

[T]he linear no threshold theory, endorsed by the U.S. National Academies of Science for decades, holds that any exposure to radioactivity, no matter how small, still carries a health risk, and such risks are cumulative over a lifetime. It would be more honest for NRC officials to states that the tritium releases from Byron are “acceptably risky,” in their judgment, but not “safe.” After all, tritium is a potent radionuclide, a clinically proven cause of cancer, mutations, and birth defects, and if inhaled, ingested, or absorbed through the skin, can integrate anywhere in the human body, right down to the DNA level.

And to add insult to the dishonestly undersold injury, the NRC says it can’t yet calculate just how much tritium escaped in this event.

But Wolf Creek and Byron were really just steamy warm ups (as it were) for January’s main event–the Grand-Guignol-meets-the-Keystone-Kops tragic-comedy commonly referred to as SONGS, or the San Onofre Nuclear Generating Station.

San Onofre sits on the California coast, about halfway between San Diego and Los Angeles, and has a long, infamous history of construction screw-ups, safety breaches, lax reporting, falsified records and unusual events. Unit 1 was brought online in 1968–and decommissioned 25 years later; Units 2 and 3 started up in the early ’80s, and are still operating today. . . .

Well, uh, about that. . . .

Officials at the San Onofre nuclear power plant shut down one of the facility’s two units Tuesday evening [January 31] after a sensor detected a possible leak in a steam generator tube.

The potential leak was detected about 4:30 p.m., and the unit was completely shut down about an hour later, Southern California Edison said.

The next day, SCE revealed that yes, indeed, it was a leak that caused them to scram Unit 3, and that they were dealing with it by “reducing pressure“. . . which other people might call “venting.” SONGS is also a PWR, and this leak was also in the loop that spins the turbines and not the one that runs through the reactor, but as noted above, that system still contains some radionuclides. Edison does admit to the release of some radiation, though they make the same “no threat/no harm” assertions common to the other unusual events.

Beyond the usual pushback on that “no harm” claim, it should also be noted here that the leak did no occur in the reactor’s sealed containment building, but in an auxiliary building. . . with doors. . . and people that go in and out through those doors. . . so the question is not whether some radiation escaped into the atmosphere, but “how much?”

But that’s not the scary part.

The leak occurred in Unit 3, and so that had to be shut down, but Unit 2 was already down–offline for two months of refueling and repair. However, the accident in Unit 3 prompted quite the revelation about Unit 2:

Unusual wear has been found on hundreds of tubes that carry radioactive water at Southern California’s San Onofre Unit 2 nuclear plant, raising questions about the integrity of equipment the company installed in a multimillion-dollar makeover in 2009.

. . . .

The problems at Unit 2 were discovered during inspections of a steam generator, after the plant 45 miles north of San Diego was taken off-line for maintenance and refueling. The two huge steam generators at Unit 2, each containing 9,700 tubes, were replaced in fall 2009, and a year later in its twin plant, Unit 3, as part of a $670 million overhaul.

According to the Nuclear Regulatory Commission, more than a third of the wall had been worn away in two tubes at Unit 2, which will require them to be plugged and taken out of service. At least 20 percent of the tube wall was worn away in 69 other tubes, and in more than 800, the thinning was at least 10 percent.

This level of wear might be typical to systems in use for several decades–still not comforting, considering the age of America’s nuclear plants–but to see this degradation in virtually new tubes gives one pause. . . especially one Joram Hopenfeld, retired NRC engineer and researcher:

“I’ve never heard of anything like that over so short a period of time,” Hopenfeld said.

“The safety implications could be very, very severe,” Hopenfeld added. “Usually the concern is in older steam generators, when they have cracks all over the place.”

According to the regulatory commission, the tubes have an important safety role because they represent one of the primary barriers with the radioactive side of the plant. If a tube breaks, there is the potential that radioactivity from the system that pumps water through the reactor could escape into the atmosphere.

About two-thirds of US reactors are of similar design to those at SONGS.

That’s the scary part.

It is scary, of course, because it raises questions about the manufacturing, the installation, and the maintenance of the $670 million rehab at San Onofre–but it also should raise concerns about the repairs, refurbishments and retrofits at dozens of other domestic facilities.

And it also provides another object lesson on the real costs of nuclear power. To put it in context, the San Onofre makeover cost $135 million more than the much-maligned federal loan guarantee extended in 2009 to the now-defunct solar panel manufacturer Solyndra Corporation. (And, unlike it could ever be for a nuclear loan guarantee, the federal government will recoup most of the Solyndra money when company assets are sold.)

Atomic energy advocates will argue that while construction costs are high, once built, nuclear plants run pretty much round-the-clock–24/7/365, as they say.

Except, of course, as the events just described or any of the dozens of other incidents documented here over the last year show, they don’t. Right now, SONGS is generating zero power. None. The same can be said for Wolf Creek, and one of the two reactors at Byron. The Palisades plant in Michigan was shut down five times last year. Ohio’s Davis-Besse facility, offline much of 2011 because of major repairs and a series of questions about cracks in the reactor building, was just given the green light to restart by the NRC, despite the objections of many nuclear watchdogs and US Rep. Dennis Kucinich (D-OH).

Reactors at North Anna, VA, Calvert Cliffs, MD, and Fort Calhoun, NE, were all offline for substantial amounts of time in 2011. A swarm of jellyfish took out Florida’s St. Lucie nuclear plant for several days last summer, and Crystal River, also in Florida, has not produced so much as a single kilowatt in almost two-and-a-half years. And it likely won’t produce any more until 2014 at the earliest, assuming Florida ratepayers pony up another $2.5 billion for repairs.

All of which again underscores that nuclear power is not just phenomenally expensive in every phase of its life, it is an expense always born by ratepayers and taxpayers. And that, of course, just refers to the financial costs.

Those tritium leaks will take some toll on the health of residents in regions near Byron and SONGS, though it will debated just how much. Less debatable now–thanks to a French study released, yes, in January–the everyday dangers of having a nuclear facility in your general area:

In a report certain to cause fear and loathing in the global nuclear industry, an eminent French research institute published a study in the International Journal of Cancer, which notes increased rates of leukemia in children living close to French nuclear power plants (NPPs.)

How much greater?

The study by the Institut National de la Sante et de la Recherche Medicale (French Institute of Health and Medical Research, or INSERM) found a leukemia rate twice as high among children under the age of 15 living within a 3.1-mile radius of France’s 19 nuclear power plants.

France, of course, has a universal health plan, so those costs will directly hit their national budget. The US does not embrace a similar level of responsibility for the health of its citizens, but the costs of increased numbers of childhood cancers will ripple through the economy all the same (well, in reality, even more then all the same).

Still feeling nuclear power’s worst year is behind it?

But, wait, there’s more–a sort of microcosmic calamity to put a grace note on nuclear’s macro-farce: A few days before the leak and the revelations about tube decay, an Edison employee at San Onofre fell into a fuel storage pool while trying to retrieve a dropped flashlight. The worker was not injured in the fall, though he did ingest some unspecified amount of radioactive water–but (and you know what’s coming here. . . wait for it. . . wait for it) SCE said the man “did not suffer harmful radiation exposure.”

Welcome to 2012. One mensis horribilis down, 11 to go.

NRC Gives OK for Restart of Damaged North Anna Nuclear Plant

North Anna Nuclear Generating Station (photo: dougward)

In what feels like a Friday news dump that goes to 11, the US Nuclear Regulatory Commission has given its approval to restart Dominion Virginia Power’s North Anna nuclear power facility. The decision came late in the day on a holiday–Veterans Day, 11/11/11.

As previously noted, the reactors at North Anna scrammed during the Mineral, VA earthquake of August 23. It was later shown the power plant sustained shaking well beyond its design criteria. Several spent fuel storage casks moved one to four inches, and other storage containers showed what was termed cosmetic damage (namely, cracks), but plant operators contend that the nuclear reactors sustained no “functional” damage.

What constitutes “functional” now remains to be seen. The fact is there was no official protocol–no “checklist”–for evaluating a nuclear facility after it experienced a seismic event such as this. The NRC’s inspectors have essentially been inventing that inspection regime on the fly as they surveyed the North Anna plant. Dominion has been pressing for permission to restart since shortly after the quake.

Of concern, beyond the cracks and dancing dry casks, has been the integrity of the containment buildings and, more specifically, the pipes and couplings that ensure that the reactors can be properly cooled once the cores are allowed to again heat up. Questions about the state of underground pipes were expressed right after the earthquake by watchdogs such as Paul Gunter, and those same buried pipes were cited as recently as last week when explaining the ongoing delay to the restart OK.

North Anna’s reactors were initially thought to have shut down when the cooling systems lost power from the electrical grid, soon after the Virginia quake. Three backup diesel generators provided power to the safety systems until power could be restored (a fourth generator failed). Later, however, it was discovered that the shaking itself caused the reactors to scram–a fast emergency shutdown sometimes compared to slamming the brakes on a speeding car.

How the NRC and its inspectors resolved questions about what constituted a passing grade after a never-before-seen event remains to be seen. Until then, it appears the NRC will do the regulatory equivalent of keeping its fingers crossed:

Eric Leeds, director of the NRC’s Office of Nuclear Reactor Regulation, said in a statement. “We’re satisfied the plant meets our requirements to restart safely, and we’ll monitor Dominion’s ongoing tests and inspections during startup of both reactors.”

Let’s hope inspectors work holidays.

NRC Chair Jaczko: Events Like Fukushima Too Rare to Require Immediate Changes

NRC, nuclear

NRC Chair Gregory Jaczko (photo: Gabrielle Pffaflin/TalkMediaNews)

For those that think nothing has changed in United States regulation since the Japanese earthquake and tsunami started the ongoing crisis at the Fukushima Daiichi nuclear facility, think again. The pre-disaster mentality of “What could possibly go wrong?” has been replaced with reassurances that “Stuff like that hardly ever happens!”

At least that is the impression conveyed by the current chairman of the US Nuclear Regulatory Commission, Gregory Jaczko, in a pair of early October interviews. During two NRC-sponsored events, Jaczko fielded questions first from nuclear industry professionals and those considered friendly to the expansion of nuclear power, and then, in a separate session two days later, responded to representatives from public interest groups and other individuals generally seen as opposed to nuclear energy.

While the tone of the questions differed somewhat predictably in the two sessions, Chairman Jaczko’s attitude did not. Jaczko took several opportunities to praise the NRC staff and the processes and protocols used by the commission, repeating in both panels that the primary duty of his agency is ensuring the safety of nuclear facilities in the United States.

Beyond his broad assurances and patient, capable demeanor, however, many of the chairman’s assertions about both the NRC process and the progress being made toward his stated safety goals highlighted notable contradictions and troubling biases inherent in America’s nuclear regulatory regime.

To be fair, the pre-Fukushima outlook was not exactly “What could possibly go wrong?” In terms of the types of accidents and the repercussions of contamination, containment breaches, radioactive releases, meltdowns, melt-throughs, and a host of other undesirable situations, regulators and industry insiders alike were probably quite aware of what could go wrong. But as US nuclear proponents and profiteers strove to convey the impression of an informed industry, they also moved to downplay the threats to public safety and made sure to stress that, when it came to disaster scenarios, they had it covered.

If the disaster in Japan has proven one thing, though, it is that plant operators and nuclear regulators didn’t have it covered. Events (or combinations of events) that were either not foreseen or not acknowledged leave Japan scrambling to this day to understand and mitigate an ever-evolving catastrophe that has contaminated land and sea, and exposed yet-untallied thousands of Japanese to dangerous levels of radiation. “As we saw in Fukushima,” said Jaczko, “accidents still do happen in this industry. If we are thinking that they can’t, we are in a dangerous place.”

But for US nuclear regulators, there needn’t be any sense of urgency–or so believes the NRC chair. When asked why the agency doesn’t hold up plant relicensing until new standards that include lessons learned from the Japanese disaster are in place, Jaczko expressed confidence in the current system:

Bottom line is that changes get made at a plant. . . some changes will be made quickly, some may take years. It doesn’t matter where a plant is [in the process]–what is the licensing phase–but that changes get made. These are low frequency events, so we have some leeway.

It is a posture Jaczko took again and again in what totaled over two-and-a-half hours of Q&A–accidents are very, very rare. Given the history of nuclear power, especially the very recent history, his attitude is as surprising as it is disturbing. Beyond the depressingly obvious major disasters in nuclear’s short history, unusual events and external challenges now manifest almost weekly in America’s ageing nuclear infrastructure. The tornado that scrammed Browns Ferry, the flooding at Fort Calhoun, the earthquake that scrammed the reactors and moved storage casks at North Anna and posed problems for ten other facilities, and Hurricane Irene, which required a number of plants to take precautions and scrammed Calvert Cliffs when a transformer blew due to flying debris–all are external hazards that affected US facilities in 2011. Add to that two leaks and an electrical accident at Palisades, stuck valves at Diablo Canyon, and failures in the reactor head at oft-troubled Davis Besse, and the notion that dangerous events at nuclear facilities are few and far between doesn’t pass the laugh test.

That these “lesser” events have not resulted in any meltdowns or dirty explosions does nothing to minimize the potential harm of a more serious accident, as has been all too vividly demonstrated in Japan. The frequency or infrequency of “Level 7” disasters (the most severe event rating–so far given to both Chernobyl and Fukushima) cannot be used to paper-over inadequate safeguards when the repercussions of these catastrophes are so great and last for generations.

Storage concerns don’t concern

Chairman Jaczko’s seeming ease with passing current problems on to future generations was also in evidence as he discussed mid- and long-term storage of spent nuclear fuel. Though previously a proponent of an accelerated transfer of spent fuel from pools to dry casks, Jaczko now says, post-Fukushima, he has “no scientific evidence that one method is safer than the other.” The chairman made a point of noting that some dry casks at Virginia’s North Anna plant moved during the August earthquake, but said that it will be well over a year before we can evaluate what happened to wet and dry storage systems at Fukushima.

While it is true a full understanding will have to wait until after Daiichi is stabilized and decontaminated, it is already apparent that the spent fuel pools, which require a power source to actively circulate water and keep the stored fuel cool, posed dangers that in some ways rivaled the problems with the reactors. (So far, no Japanese plants have reported any problems with their dry casks.) So obvious was this shortcoming, that the NRC’s own staff review actually added a proposal to the Fukushima taskforce report, recommending that US plants take more fuel out of wet storage and move it to dry.

Jaczko’s newfound indifference is also odd in light of his own comments about dry casks as an alternative to a central nuclear waste repository. Asked in both sessions about the closing of Yucca Mountain (the proposed US site for spent nuclear fuel), the chairman buoyantly championed the possibility of using on-site dry casks for hundreds of years:

The commission is taking the appropriate action to address the storage of spent fuel. We have come to the conclusion that, over the short- and medium-term, safe storage is possible. We are taking a look at what is the finite limit on current [dry] storage. . . 200, 300, 400 years. Is there a time we have to move the fuel? . . . Nothing tells us we shouldn’t generate the [radioactive] material. We don’t see a safety concern out 100 years, or anything that says at 101 years, everything changes.

Chairman Jaczko then added that while the nuclear industry is generating waste that will require “long, long term storage or isolation,” it is not unprecedented to assume this problem can be taken care of by “future generations.”

It is good that Jaczko has such faith in the future, because his depiction of the present is not actually that impressive. While the NRC chief repeatedly touted their “process” for evaluating risks, problems, and proposals, he also painted a picture of a bureaucracy that has so far failed to fully act on the initiatives he has considered most important. Neither the fire-safety improvements Jaczko has championed since he came to the commission in 2005, nor the security enhancements required after 9/11/2001 have as yet been fully implemented.

Process is everything

Time and again, whether he was directly challenged by a question or simply asked for clarification, Gregory Jaczko referred to the NRC’s “process.” “We have a relicensing process,” “there is an existing process [for evaluating seismic risk],” there is a process for determining evacuation zones, there is a process for incorporating lessons learned from Fukushima, and there is a process for evaluating new reactor designs. Process, of course, is not a bad thing–in fact, it is good to have codified protocols for evaluating safety and compliance–but stating that there is a process is not the same thing as addressing the result. Too often, what might have sounded like a reasonable answer from the chairman was, in reality, a deflection. “The process knows all; trust in the process. I cannot say what will happen, and what I want to happen does not matter–there is a process.” (This, of course, is a dramatization, not a direct quote.) Form over functionary.

But Jaczko had barely started his second session when his reliance on process suffered an “unusual event,” as it were.

Asked about why the NRC seemed to be moving full-speed ahead with relicensing, rather than pausing to wait for Fukushima taskforce recommendations to be formalized, the agency chief first said, “There is an existing program, there are processes.” But within a breath, Jaczko then said, when it comes to lessons learned from Fukushima being some sort of prerequisite for final license approval, “We are going to look on a case-by-case basis.”

Is deciding whether to apply new requirements on a “case-by-case basis” actually a process? Many would say it pretty much defines the opposite.

The counter-intuitive also took a star turn when it came time to consider new externalities and pending environmental impact surveys. Shouldn’t the Fukushima taskforce findings be considered as part of a series of new environmental impact studies? Well. . . “It is clearly new information, but does it affect the environmental impact survey? Because they are very, very low likelihood events, it is not part of the environmental impact survey.” Jaczko here seems to be saying that unless you know in advance of the new study that the new information will alter the findings, you do not need to consider new information.

Shocked, shocked

With such confidence in the commission and its process, would it be safe to assume that Greg Jaczko is comfortable with the current state of nuclear safety in the United States? Perhaps surprisingly, and to his credit, the NRC head seems to say “no.”

As previously discussed, Jaczko expected faster action on fire safety and security upgrades. He also defended his going public with complaints about design problems with the AP1000 reactors proposed for Plant Vogtle:

We had been going back and forth with [AP1000 designer] Westinghouse for two years. I felt [a lack of] openness; felt if you aired the issues, they get addressed. Now, I feel it was. . . addressed. It ultimately forced these issues to get resolved.

Chairman Jaczko was also asked what tech issues keep him up at night:

Those components that are not replaceable, not easily inspectable. Those subjected to repeated exposure to high radiation, stresses that cause high degradation.

Jaczko said he felt the commission had a handle on what radiation does to the concrete in the containment vessel, but he was less sure about the effect of “shock,” which he defined as “repeated power trips” or scrams. Jaczko acknowledged that this increases stress on the containment vessels, and added, “Some places will not have 20 years [left] on pressure vessels. We get into an unknown piece of regulation on pressure vessel repair.”

That is a pretty stark revelation from a man so passionate about his agency’s ability to, uh, process new data, but it highlights another facet of Jaczko’s approach to regulation.

Noting that New Jersey’s Oyster Creek reactor was granted a renewed operating license for 20 years, but its operator later negotiated with the state to shut it down in 10 years, Jaczko said, “Extension is an authorization to operate, not a requirement to operate.” Relicensing, he said, might come with requirements for modifications or orders that they “monitor aging.”

Jaczko also said that states or facilities might decide it is not economically viable to keep a plant running for the full length of its license, “Like if you have a car and the clutch goes and you make a decision not to replace it.”

How to regulate, even without the Regulatory Commission

Yes, another deeply flawed automobile analogy, but note that Jaczko allows for, and maybe even expects, limits to a plant’s life that are not regulated by the NRC. And in detailing such, the chief regulator of the US nuclear industry shows where citizens might exercise leverage when his NRC fails.

First, there is that issue of economic viability. As previously discussed, the market has already rendered its verdict on nuclear power. In fact, it would be absolutely impossible to build or operate a nuclear plant without loan guarantees, tax breaks, and subsidies from the federal government. The new construction at Vogtle is projected to cost nearly $15 billion (and these plants always go way over budget), and the Obama administration has had to pledge $8.33 billion in loan guarantees to get the ball rolling. Without that federal backstop, there would be no licensing battle because there wouldn’t be the possibility of the reactors getting built.

In fact, in this time of questionable nuclear safety, deficit peacockery and phony Solyndra outrage, it is illustrative to note:

. . . in FY2010 alone, $2.82 billion went to natural gas and petroleum interests (through direct expenditures, tax expenditures, research and development funds, and loan guarantees), $2.49 billion to nuclear energy interests and $1.13 billion to solar interests.

Would any of the relicensing and new construction applications be before Jaczko’s NRC if the energy-sector playing field were leveled?

Second, at many points in the interview, federal regulator Jaczko referenced the power of the states. Early in the “pro” nuclear session, an anxious question expressed worry that states such as Vermont could play a role in the relicensing of reactors. While stating it was yet to be determined whether Vermont’s authority overlapped with the NRC, its chairman stated plainly that states do play a role. “States decide what kind of generating sources they use,” Jaczko said, “especially if the state has a public utility.”

When asked in the second panel if the NRC considers whether new rules or licensing delays will cause rate hikes for consumers, Jaczko said the final determination on rates was the purview of a state’s public utilities commission:

If the PUC denies charges, then they won’t get our approval to go forward–but if the PUC denies a rate change, they [the plant operators] still have to make the improvement required.

And when discussing how the NRC draws evacuation zones, Chairman Jaczko said that in the end, it was the responsibility of the state and local governments, acting on data from the utilities and advice from the NRC, to determine where, when and how to evacuate in case of a nuclear accident.

And, yes, that does sound again like some of the buck-passing that marked too much of these interviews, but it is also a roadmap for a possible detour around a recalcitrant or captured federal agency. If activists feel shut out of the regulatory process, they can attack the funding. If federal elected officials are not responsive (because they, too, have been captured by a deep-pocketed nuclear industry), concerned citizens can hit closer to home. As Jaczko says, states can choose their power sources, and states can define evacuation protocols that either better insure public safety or reveal continued operation of nuclear facilities to be untenable.

Such action would not be easy–state and local officials have their own interests and conflicts–but it might prove easier than a broad federal play. Recent successes by those seeking to close aging coal-fired generators show that action at the individual plant level is possible.

Open to openness

For anything to happen, of course, it is important that a dedicated and passionate citizenry organize around a tactic, or, if they prefer, a process. But it will also require a level of openness on the part of government. Sometimes that openness is offered, sometimes it is hard won, but without transparency, progress is hard to make and hard to measure.

Gregory Jaczko repeatedly stated that he is a big advocate of openness, and he offered these interviews in that spirit. These two events obviously didn’t go all the way in that direction–not even close–but the sessions had merit. Chairman Jaczko, despite all the problems detailed above, can still be admired for exhibiting something rather rare in today’s political climate, a regulator that actually believes in regulation. He, in fact, conveys a passion for it. That some of that regulation is based on flawed assumptions, and that much of it is weak or never enforced, cannot be ignored, but if the head of the Nuclear Regulatory Commission advocates for the regulatory process (even when hiding behind it), then there is at least a process to improve.

* * *

A version of this story was previously posted on Truthout.

The Party Line – September 30, 2011: No Will, No Way: Nuclear Problems Persist, But US Fails to Seize Fukushima Moment

As September drew to a close, residents of southwest Michigan found themselves taking in a little extra tritium, thanks to their daily habit of breathing (h/t emptywheel). The tritium was courtesy of the 40-year-old Palisades Nuclear Generating Station in Covert Township, which suffered its third “event” (as they are politely called) in less than two months, and was forced to vent an indeterminate amount of radioactive steam.

The reactor at Palisades was forced to scram after an accident caused an electrical arc in a transformer in the DC system that powers “indications and controls“–also known as monitoring devices, meters and safety valves. (Transformer arcs seem to be “in” this season–it was a transformer arc that caused the Calvert Cliffs plant in Maryland to scram during Hurricane Irene.)

While it is nice to see rectors shut themselves down when a vital system goes offline, remember that “turning off” a fission reactor is not like flicking a light switch. Shutting down a reactor is a process, and the faster it is done, the more strain it puts on the reactor and its safety and cooling systems. And even after fission is mitigated, a reactor core generates heat that requires a fully functional cooling system.

Which is kind of an interesting point when considering that Palisades had just been restarted after completing repairs to a breach in the cooling system that was reported to be leaking more than 10 gallons per minute. Prior to that, a “special inspection” was ordered August 9 after a pipe coupling in the plant’s cooling system failed.

(By the way, have no fear, Michiganders, a public affairs representative for the Nuclear Regulatory Commission reassured the public that the concentration of tritium was “far below regulatory releases,” and that “as soon as it goes out, it gets diluted further.” You know, in the air. . . that you breathe.)

News of the Palisades tritium burp came at roughly the same time as a breathless (if a press release can be breathless) announcement from Dominion Resources, the folks responsible for the North Anna nuclear plant, the facility that scrammed after being shaken beyond design specifications by the earthquake centered in nearby Mineral, Virginia:

Our investigation showed the units tripped before the loss of off-site power when multiple reactor sensors detected a slight power reduction in the reactors. . . .

The root cause team determined that this occurred as result of vibration in the reactor or the monitoring devices in the reactors, or both.

Again, good that the reactors scrammed when something registered the quake, but noteworthy again because it was previously believed that the automatic shutdown started as a result of a loss of power–power required to operate the cooling systems, not only for the reactors, but for the spent fuel pools, as well.

While North Anna remains offline as the NRC continues its inspection (and tries to decide what would constitute passing that inspection), and Palisades is also down pending an (another) investigation, both serve as only the latest in a long string of examples in what could be called The Light Water Paradox: In order to safely generate a steady stream of electricity, a light water reactor needs a steady stream of electricity.

This is not just a perpetual motion machine laugh line. This inherent flaw in the design of LWRs is at the root of two other prominent tales of nuclear safety (or lack thereof).

The first, of course, is the ongoing, ever-metastasizing disaster in Japan, where failures in the cooling systems at Fukushima Daiichi following a massive earthquake and tsunami resulted in hydrogen explosions, core meltdowns, and, likely, melt-throughs that contaminated and continue to poison sizable portions of the country and surrounding sea.

The second story concerns the proposal for the construction of two new reactors at Plant Vogtle, a nuclear power facility near Augusta, Georgia.

The Vogtle reactors would be the first to be built in the US in a generation, and they have come under some additional scrutiny in part because they would be the first of a new-design LWR called the AP1000. A riff on previous Toshiba/Westinghouse pressurized water reactors, the AP1000’s most noticeable “innovations” are meant to address the active cooling paradox. First, it has emergency “dump tanks,” reservoirs of water situated above the reactor that could, in an emergency, empty into the reactor via gravity, providing up to 72 hours of “passive” cooling. Second, rather than housing the core in a reinforced concrete shell with a metal liner, the AP1000 would have an all-steel containment vessel which would, in theory, be able to expel heat through convection.

While these two design features both highlight and attempt to address a dangerous flaw that is a part of every other nuclear facility in the United States–that water has to be actively cycled through a reactor core to keep it from melting–the design still predates the Fukushima quake, and fails to truly incorporate the lessons of that disaster.

The massive March 11 earthquake shutdown power to the Fukushima Daiichi plant, and thus the cooling systems, and the tsunami that followed flooded the diesel-powered backup generators, but that was only part of the problem. Investigations now show that even if Fukushima had in some way managed to maintain power, the cooling system would still likely have failed for at least some (and likely all) of the reactors, and (and this is important) for the spent fuel pools, as well. That is because the quake not only caused a loss of power, it also caused numerous breaches in the cooling system. Cracks in the containment vessel, broken pipes, and dislodged couplings would have likely resulted in a calamitous drop in water levels, even with full power. Less than successful attempts to restore the cooling systems with new, external power sources, and the large amounts of contaminated water that continue to pour from the plant, have demonstrated just how severely the physical infrastructure was damaged.

There are additional concerns about the design of the AP1000 (possible corrosion of the all-metal containment vessel and less than rigorous computer modeling of seismic tolerances, for instance), but, in a post-Fukushima world, simply addressing the active/passive cooling problem (and only doing so for the reactor and not the spent fuel pools) does not promise a safe nuclear facility.

And there is, perhaps, a hint that at least one of the members of the NRC understands this:

The chairman of the U.S. Nuclear Regulatory Commission says the agency may need to incorporate its findings about a nuclear disaster in Japan into a license to build a new nuclear plant in Georgia.

NRC Chairman Gregory Jaczko said Wednesday [September 28] he believes the license to build two more reactors at Plant Vogtle near Augusta should include conditions that reflect the findings of a review of this year’s disaster at the Fukushima Dai-ichi plant.

While it is true that “may” and “should” are not “will” and “must,” and it is also the case that the Fukushima taskforce recommendations themselves do not fully address the problem outlined here, Chairman Jaczko’s comments do make the point that there are indeed lessons to be learned from the Japanese crisis, and right now, in the US, that education has not taken place.

The chairman and his fellow commissioners have wrestled all summer with the pace of post-Fukushima reform. Jaczko has argued for what in NRC terms is considered a speedy consideration of the new safety regime, but a majority of the panel has managed to slow the process down to a point where no new regulations will likely be in place by the time the NRC is required to rule on the Vogtle permits.

But, because the Vogtle hearings have revealed the Chairman’s understanding of at least some of the problems, it also reveals an obvious path for Jaczko and those (such as Senator Barbara Boxer (D-CA)) who would also want any new construction or operating permits to only be approved under guidelines drafted in response to the Fukushima disaster. If the industry–and the commissioners most friendly to it–wants to move quickly ahead on new construction and the relicensing of 40-year-old plants, then it should be required that they move quickly on adopting the Fukushima taskforce recommendations. No new safety rules, no new permits–the political calculus should be that simple.

And, if the NRC won’t do the political math, then it should be up to elected government to run the financial numbers.

Building the new Vogtle reactors is projected to cost $14.8 billion. That’s projected–the existing Vogtle plant went over budget by a factor of 14. But even if the new reactors stay on budget, there is still no way they would get built without help from the Federal Government. To that end, the Obama administration okayed an $8.33 billion loan guarantee for The Southern Company, owners of Plant Vogtle, contingent on the NRC’s approval of the plans. (By way of comparison, that is 16 times the size of the loan given to the now-defunct solar technology company Solyndra.) While there are a myriad of reasons why that and other such guarantees should never be proffered, at minimum, the federal government should now freeze the financial backing for new construction until the NRC passes–and industry adopts–an enhanced safety regime.

This wouldn’t be a one-shot power play. Hot on the heals of Vogtle, the V.C. Summer nuclear facility in South Carolina is also looking to add two new AP1000 reactors, and its permit process is also underway. And financial markets understand what a bad bet that project is, too. Summer is also owned by Southern, but it is operated by SCANA. Moody’s, the bond-rating agency, just downgraded SCANA’s debt to one notch above “junk” status, citing the cost of the proposed new reactors.

Meanwhile, the Commonwealth of Virginia has handed over $7 million in precious state funds to North Carolina’s Babcock & Wilcox to open a prototype of a small modular reactor (SMR) in the town of Forest, near Lynchburg. The SMR is small, indeed–160 megawatts (in contrast to the 1,800 megawatt capability of Virginia’s North Anna plant)–and it’s built entirely underground, supposedly enhancing its safety when faced with a potential terrorist attack. How it will provide greater protection from an earthquake or flood seems (at best) less obvious.

Yet, with all of this action, all of these new designs, all of this lobbying, and all of this (as “serious” people repeatedly caution) scarce government money, still no one is addressing another part of the nuclear equation: spent fuel. With Yucca Mountain now (supposedly) abandoned, the United States has no long-term plan for handling the already large and ever-growing problem of dangerous spent nuclear fuel. Right now, each nuclear facility stores its used fuel in either pools, dry casks, or both. The spent fuel pools require an active cooling system, which faces most of the same problems inherent in reactor cooling. Dry casks–used for fuel that is cool enough to remove from the pools–are considered safer, but they are far from “safe.” They are above ground, emit some radiation, and are theoretically vulnerable to terrorist attack (and the casks at North Anna moved and sustained “cosmetic” cracks in the August earthquake). In many US plants, both pools and casks are already filled to capacity. Expanding the number of nuclear reactors only accelerates the storage crisis.

And it must be reiterated, all of this activity comes a mere six months after the start of the Fukushima disaster. The latest announcement from the Japanese government–that they will relax the evacuation order for more than 100,000 residents even though their towns have not yet been decontaminated–says nothing about an easing of the emergency, and everything about a government that frankly just doesn’t know what else to do. The United States, though obviously larger, has reactors near enough to densely populated areas that a nuclear accident would make Japan’s evacuation problem seem like a rush hour fender bender. And the US government’s plan to deal with a nuclear disaster is no more impressive than Japan’s.

The saddest part, of course, is that it needn’t be that way. Beyond the political and financial tools proposed above, the NRC actually already has the power to demand the nuclear industry own up to the new seismic reality. When Westinghouse Electric came before the commission in May, it was ordered to fix its seismic calculations. Though Westinghouse grumbled, it did not question the NRC’s authority to rule on seismic concerns.

David Lochbaum, director of the Nuclear Safety Project at the Union of Concerned Scientists, agrees that the NRC has all the authority it needs:

Nuclear regulators already have “sufficient information and knowledge” to deal with earthquake risks at existing U.S. reactors and don’t need to wait for a broader review, a safety advocate said.

The Nuclear Regulatory Commission developed seismic rules for new plants in 1996 and has since approved preliminary construction for proposed nuclear units at a Southern Co. plant in Georgia and certified an early reactor design by Toshiba Corp.’s Westinghouse Electric unit, according to comments filed with the agency today by David Lochbaum. . . .

“If the NRC truly lacks sufficient information about seismic hazards and how safety at nuclear power reactors is affected, then the agency cannot responsibly have issued early site permits and certified new reactor designs,” he said.

Of course, having the authority and exercising it are not the same thing, but just as the NRC is not truly handcuffed by the fight over the Fukushima taskforce recommendations, the entire country need not be shackled to such a flawed, dangerous and expensive energy source as nuclear. The US government has demonstrated that it has the authority to make decisions on energy sources, and it has shown that it actually has the money to invest–big money. Of course, be it the NRC, Congress or President Obama, when it comes to moving beyond nuclear to demonstrably safer and truly renewable sources, what the US has not shown is the will.

– – –

Correction: Last week’s post included the wrong location for the Seabrook nuclear plant; Seabrook is in New Hampshire. Apologies and thanks to the readers that spotted the error.